Simple Wins / Australian Red Tape Every step, every clock, every authority -- written down.

Department of Climate Change, Energy, the Environment and Water (DCCEEW)

Assesses and approves actions under the EPBC Act

The Commonwealth environment department administers the referral, assessment and approval of actions likely to have a significant impact on a matter of national environmental significance. Its decisions run alongside state planning approval, not instead of it.

Responsibilities

Operates under

This body matters to the database out of proportion to how often it appears. It is rarely the first approval a project needs and almost never the last, but where it is triggered it commonly becomes the longest single step in the chain -- and, unusually, it is a step running on a clock the state process cannot see and does not coordinate with.

Two structural features are worth recording separately from any argument about whether the assessment itself is worthwhile.

First, the statutory clocks are expressed in business days and stop whenever the department requests further information. A twenty business day decision is about a calendar month at best, and considerably longer whenever the clock is stopped. Statutory time and elapsed time are not the same quantity here, and only elapsed time is what a proponent experiences.

Second, the department has been audited on timeliness. The Auditor-General found in 2020 that administration of referrals, assessments and approvals was not effective, and that statutory timeframes were met in 19 per cent of cases in the fourth quarter of 2019. Reported performance after subsequent funding was substantially better, at 87 per cent. That range -- 19 per cent to 87 per cent on the same statutory clock, with the law unchanged -- is the strongest evidence in this database that a large share of approval delay is a resourcing and queueing question rather than a legislative one.

Anyone proposing to fix environmental approval delay by amending the Act has to explain that range first.

Where this body appears in a process

Every point at which Department of Climate Change, Energy, the Environment and Water can hold something up, and why.

ProcessStepWhy it waitsClockTypical
Acquire a major defence capability Facilities, environmental and works approvals referral assessment — 400
Commonwealth environmental approval for a residential subdivision Refer the action to the department application applicant — 5
Commonwealth environmental approval for a residential subdivision Controlled action decision decision assessment 28 40
Commonwealth environmental approval for a residential subdivision Decision on assessment approach decision assessment 28 30
Commonwealth environmental approval for a residential subdivision Public comment on the documentation notification statutory 20 20
Commonwealth environmental approval for a residential subdivision Departmental assessment and recommendation report assessment queue — 90
Commonwealth environmental approval for a residential subdivision Approval decision and conditions decision assessment 56 60
Environmental and planning approval for high speed rail — Newcastle to Sydney Refer the action under the EPBC Act application applicant — 10
Environmental and planning approval for high speed rail — Newcastle to Sydney Controlled action decision decision assessment 28 40
Environmental and planning approval for high speed rail — Newcastle to Sydney Commonwealth public comment period notification statutory 20 20
Environmental and planning approval for high speed rail — Newcastle to Sydney Commonwealth recommendation report assessment queue — 120
Environmental and planning approval for high speed rail — Newcastle to Sydney Commonwealth approval and conditions decision assessment 56 60
A container terminal is approved at an Australian port EPBC referral and controlled action decision referral statutory 28 28
A container terminal is approved at an Australian port EPBC assessment and approval assessment assessment — 365
A container terminal is approved at an Australian port Sea dumping permit for dredge spoil application assessment 90 365
Build a major transmission line — sequential easement pathway Commonwealth environmental approval decision assessment — 980
A water infrastructure project reaches construction funding EPBC assessment and approval assessment assessment — 365
Deliver a new public hospital — New South Wales EPBC Act referral, where triggered referral third party 28 28
Build a major transmission line — concurrent easement pathway (Victoria) Commonwealth environmental approval decision assessment — 540