Raw Aus Pol

Simple Wins / Australian Red Tape Every step, every clock, every authority -- written down.

Build a major transmission line — sequential easement pathway

Two cost-benefit tests, two environmental assessments, and an easement acquisition that cannot start until the assessment finishes. The delays that have actually bitten are in the last of those, not the first.

energyA multi-hundred-kilometre high voltage transmission line designated actionable in the Integrated System Plan, crossing private agricultural land draft compare across jurisdictions
4110 days elapsed
longest dependent chain
10 discrete steps
across 5 bodies
0% waiting on availability
scheduling or queue, not assessment
1204 days saved by concurrency
vs. 5314 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

assessment 1886d Someone is genuinely evaluating the merits.
third party 1080d Waiting on an external body outside the regulator's control.
applicant 900d Waiting on the applicant to supply or fix something.
statutory 244d A legislated period that must elapse regardless of readiness.

The process, step by step

Applies when: An actionable ISP project where compulsory easement acquisition may only commence after environmental assessment concludes.

#StepWhoWhy it waits ClockTypicalBasis
1 Identified as an actionable project in the Integrated System Plan assessment
A whole-of-system cost-benefit process concludes the project is needed and designates it actionable.
Australian Energy Market Operator assessment — 365 estimate —
2 Project specification consultation report and consultation notification
First stage of the regulatory investment test: the identified need and credible options are published for consultation.
Transmission network service provider statutory — 199 published National Electricity Rules, clause 5.16.4 (not part of the clause 5.16A procedure for actionable ISP projects)
3 Project assessment draft report and consultation notification
The draft report is published and submissions are sought on the proposed preferred option.
Transmission network service provider statutory 42 45 legislated National Electricity Rules, clause 5.16A.4
4 Project assessment conclusions report decision
Final stage of the regulatory investment test, concluding which option maximises net market benefit.
Transmission network service provider assessment — 521 published National Electricity Rules, clause 5.16A.4
5 Contingent project application and revenue determination decision
The transmission business applies to recover the project's capital expenditure from consumers.
Australian Energy Regulator assessment 56 224 published National Electricity Rules, clause 6A.8.2
6 Route selection and landholder engagement application
Refine the corridor, negotiate access for survey, and begin easement negotiations with affected landholders.
Transmission network service provider third party — 540 estimate —
7 Commonwealth environmental approval decision Department of Climate Change, Energy, the Environment and Water assessment — 980 published Environment Protection and Biodiversity Conservation Act 1999 (Cth)
8 State planning approval and environmental assessment decision
Assessment as state significant infrastructure, including environmental impact statement, exhibition and submissions.
NSW Department of Planning, Housing and Infrastructure assessment — 1000 published Environmental Planning and Assessment Act 1979 (NSW), Division 5.2
9 Easement acquisition registration
Acquire the easements the corridor requires, by agreement or compulsorily.
Transmission network service provider third party — 540 estimate —
10 Construction and commissioning application Transmission network service provider applicant — 900 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

Proposed changes

  • Assess once under an accredited state process, decide twice merge ~150d
    Where a project needs both state and Commonwealth environmental approval, two documents are prepared, two consultations are run and two assessments are performed on the same impacts. Assessment bilateral agreements already allow one assessment to serve both decisions — they are simply not in place for most of the country.
  • Test an actionable ISP project once, not twice merge ~300d
    A project identified as needed by a whole-of-system cost-benefit process then runs its own three-stage cost-benefit process to establish that it is needed. The actionable ISP framework was built to remove that duplication and removed only part of it.
  • Let easement acquisition run alongside environmental assessment, not after it parallelise ~540d
    Victoria amended its law in 2026 so compulsory easement acquisition for transmission can proceed concurrently with the environment effects process, having identified the sequential requirement as a cause of delay on VNI West and the Western Renewables Link. Modelled against the sequential pathway, one dependency edge is worth about eighteen months.

Sources

  1. National Electricity Rules, rule 5.15A (regulatory investment test for transmission)
  2. AEMO, Integrated System Plan and actionable project framework
  3. AER, published RIT-T and application guidelines, and contingent project application process
  4. Reporting on VNI West completion moving from 2028 to late 2030 on landholder engagement and assessment
  5. Cost benefit analysis guidelines (Version 3, November 2024), Australian Energy Regulator, https://www.aer.gov.au/system/files/2025-05/AER%20-%20Cost%20Benefit%20Analysis%20guidelines%20-%202024%20-%20Version%203.pdf, accessed 2026-11-09
  6. Transgrid, HumeLink regulatory and environmental approvals documents (PSCR 25 June 2019, PADR 10 January 2020, PACR 29 July 2021), https://www.transgrid.com.au/projects-innovation/humelink/regulatory-updates-and-documents/, accessed 2026-11-09
  7. HumeLink (SSI 36656827) Assessment Report, NSW Department of Planning, Housing and Infrastructure, October 2024, https://transgrid.com.au/media/wf4pmmx3/assessment-report.pdf, accessed 2026-11-09