Deliver a new public hospital — New South Wales

Most of the calendar here is construction, and that is not red tape. The finding is at the front end: the years between identifying that a hospital is needed and being permitted to start designing it, a large part of which is waiting for a budget round rather than waiting for an answer.

health-infrastructureMajor hospital redevelopment, capital value above the state's high-risk assurance threshold skeleton compare across jurisdictions
2975 days elapsed
longest dependent chain
11 discrete steps
across 4 bodies
11% waiting on availability
scheduling or queue, not assessment
0 days saved by concurrency
vs. 2975 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 1640d Waiting on the applicant to supply or fix something.
assessment 1020d Someone is genuinely evaluating the merits.
scheduling 315d Waiting for a person or committee to become available.

315 of 2975 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A local health district identifies a service need requiring major capital investment.

#StepWhoWhy it waits ClockTypicalBasis
1 Clinical services plan application
Establish projected demand, service model and the case that capital is the answer.
Health Infrastructure NSW assessment — 270 estimate —
2 Strategic business case application
after Clinical services plan 2525d slack
Health Infrastructure NSW applicant — 180 estimate —
3 Gateway review: strategic assessment assessment
Independent review of the strategic business case under the state assurance framework.
after Strategic business case 2465d slack
NSW Treasury (Infrastructure Investor Assurance) scheduling — 60 estimate —
4 Final business case application
Detailed costing, options analysis, site selection and delivery strategy.
Health Infrastructure NSW applicant — 365 estimate —
5 Gateway review: business case assessment
after Final business case 2025d slack
NSW Treasury (Infrastructure Investor Assurance) scheduling — 75 estimate —
6 Capital funding decision in the budget decision
The project competes for capital allocation in the annual budget.
NSW Treasury (Infrastructure Investor Assurance) scheduling — 180 estimate —
7 Planning approval as state significant development decision NSW Department of Planning, Housing and Infrastructure assessment — 300 estimate Environmental Planning and Assessment Act 1979 (NSW), Division 4.7
8 EPBC Act referral, where triggered referral only if triggered
Triggered when: The site supports a matter of national environmental significance, which for a brownfield hospital redevelopment is uncommon.
Department of Climate Change, Energy, the Environment and Water third party 28 28 legislated Environment Protection and Biodiversity Conservation Act 1999 (Cth), s 75
9 Procure the delivery contractor application Health Infrastructure NSW assessment — 270 estimate —
10 Construction application Health Infrastructure NSW applicant — 1095 estimate —
11 Commissioning, accreditation and licensing certification
Health service accreditation, licensing of regulated facilities, and clinical commissioning before patients arrive.
Health Infrastructure NSW assessment — 180 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

  • EPBC Act referral, where triggered is a referral queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?

The same body asked more than once

Proposed changes

Sources

  1. NSW Treasury, published Infrastructure Investor Assurance Framework and gateway review requirements
  2. Infrastructure Partnerships Australia, 'A Healthy Pipeline: Delivering Australia's Hospital Infrastructure'
  3. Auditor-General for South Australia, 2025 findings on delays in commencing construction on major hospital projects
  4. Health capital works (performance audit, 2020), Audit Office of New South Wales, https://www.audit.nsw.gov.au/our-work/reports/health-capital-works, accessed 2026-11-09
  5. Gateway Workbook: Gate 2 Business Case, Version 3, June 2021, Infrastructure NSW, https://www.infrastructure.nsw.gov.au/media/q0jbrpc5/gate-2-gateway-workbook_v3-june-2021.pdf, accessed 2026-11-09
  6. Gateway Workbook: Gate 1 Strategic Options, Version 6, March 2026, Infrastructure NSW, https://infrastructure.nsw.gov.au/media/bdwghlab/gate-1-gateway-workbook-v5-nov-2024.pdf, accessed 2026-11-09