Deliver a new public hospital — New South Wales
Most of the calendar here is construction, and that is not red tape. The finding is at the front end: the years between identifying that a hospital is needed and being permitted to start designing it, a large part of which is waiting for a budget round rather than waiting for an answer.
longest dependent chain
across 4 bodies
scheduling or queue, not assessment
vs. 2975 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 1640d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 1020d | Someone is genuinely evaluating the merits. | |
| scheduling | 315d | Waiting for a person or committee to become available. |
315 of 2975 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A local health district identifies a service need requiring major capital investment.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Clinical services plan
application
Establish projected demand, service model and the case that capital is the answer. |
Health Infrastructure NSW | assessment | — | 270 estimate | — |
| 2 |
Strategic business case
application
after
Clinical services plan 2525d slack
|
Health Infrastructure NSW | applicant | — | 180 estimate | — |
| 3 |
Gateway review: strategic assessment
assessment
Independent review of the strategic business case under the state assurance framework. after
Strategic business case 2465d slack
|
NSW Treasury (Infrastructure Investor Assurance) | scheduling | — | 60 estimate | — |
| 4 |
Final business case
application
Detailed costing, options analysis, site selection and delivery strategy. after
Gateway review: strategic assessment 2100d slack
|
Health Infrastructure NSW | applicant | — | 365 estimate | — |
| 5 |
Gateway review: business case
assessment
after
Final business case 2025d slack
|
NSW Treasury (Infrastructure Investor Assurance) | scheduling | — | 75 estimate | — |
| 6 |
Capital funding decision in the budget
decision
The project competes for capital allocation in the annual budget. after
Gateway review: business case 1845d slack
|
NSW Treasury (Infrastructure Investor Assurance) | scheduling | — | 180 estimate | — |
| 7 |
Planning approval as state significant development
decision
after
Capital funding decision in the budget 1545d slack
|
NSW Department of Planning, Housing and Infrastructure | assessment | — | 300 estimate | Environmental Planning and Assessment Act 1979 (NSW), Division 4.7 |
| 8 |
EPBC Act referral, where triggered
referral
only if triggered Triggered when: The site supports a matter of national environmental significance, which for a brownfield hospital redevelopment is uncommon. after
Capital funding decision in the budget 1817d slack
|
Department of Climate Change, Energy, the Environment and Water | third party | 28 | 28 legislated | Environment Protection and Biodiversity Conservation Act 1999 (Cth), s 75 |
| 9 |
Procure the delivery contractor
application
after
Planning approval as state significant development 1275d slack
|
Health Infrastructure NSW | assessment | — | 270 estimate | — |
| 10 |
Construction
application
after
Procure the delivery contractor 180d slack
|
Health Infrastructure NSW | applicant | — | 1095 estimate | — |
| 11 |
Commissioning, accreditation and licensing
certification
Health service accreditation, licensing of regulated facilities, and clinical commissioning before patients arrive. after
Construction
|
Health Infrastructure NSW | assessment | — | 180 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
Steps that may not need to wait
- EPBC Act referral, where triggered is a referral queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?
The same body asked more than once
- nsw-treasury-gateway (assessment) appears at Gateway review: strategic assessment, Gateway review: business case. Could these be a single sign-off?
Proposed changes
-
Let hospital design proceed while the funding decision waits for the budget
parallelise
~180d A hospital business case finished in August is not assessed sooner for being finished early. It waits for the next budget. Averaged over arrival dates that is about half a year in which the project is complete, reviewed, and waiting for a date in the fiscal calendar.
Sources
- NSW Treasury, published Infrastructure Investor Assurance Framework and gateway review requirements
- Infrastructure Partnerships Australia, 'A Healthy Pipeline: Delivering Australia's Hospital Infrastructure'
- Auditor-General for South Australia, 2025 findings on delays in commencing construction on major hospital projects
- Health capital works (performance audit, 2020), Audit Office of New South Wales, https://www.audit.nsw.gov.au/our-work/reports/health-capital-works, accessed 2026-11-09
- Gateway Workbook: Gate 2 Business Case, Version 3, June 2021, Infrastructure NSW, https://www.infrastructure.nsw.gov.au/media/q0jbrpc5/gate-2-gateway-workbook_v3-june-2021.pdf, accessed 2026-11-09
- Gateway Workbook: Gate 1 Strategic Options, Version 6, March 2026, Infrastructure NSW, https://infrastructure.nsw.gov.au/media/bdwghlab/gate-1-gateway-workbook-v5-nov-2024.pdf, accessed 2026-11-09
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/nsw-hospital-capital.toml and open a pull request, or
send us the correction.