Acquire a major defence capability

Years of analysis and gates before a contract is signed, none of it on a statutory clock, none of it with published elapsed times, and none of it reviewable by anyone outside Defence.

defenceA major capital acquisition in the Integrated Investment Program, passing through the Capability Life Cycle to government second pass approval and contract skeleton compare across jurisdictions
5540 days elapsed
longest dependent chain
10 discrete steps
across 2 bodies
10% waiting on availability
scheduling or queue, not assessment
0 days saved by concurrency
vs. 5540 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 2555d Waiting on the applicant to supply or fix something.
assessment 2445d Someone is genuinely evaluating the merits.
scheduling 540d Waiting for a person or committee to become available.

540 of 5540 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A capability need is identified that requires government approval and a major acquisition contract.

#StepWhoWhy it waits ClockTypicalBasis
1 Capability need identified and entered in the investment program application Department of Defence assessment — 365 estimate —
2 Gate 0: strategy and concepts decision
Internal endorsement that the need is real and warrants development.
Department of Defence scheduling — 180 estimate —
3 Risk mitigation and requirement setting assessment
Options analysis, industry engagement, cost and schedule estimation, and requirements definition.
Department of Defence assessment — 730 estimate —
4 Gate 1: government first pass approval decision
Government approves the options to be developed and the funding to develop them.
Department of Defence scheduling — 180 estimate —
5 Solicitation and tender evaluation assessment Department of Defence assessment — 540 estimate —
6 Gate 2: government second pass approval decision
Government approves the acquisition and the funding.
Department of Defence scheduling — 180 estimate —
7 Contract negotiation and execution decision Department of Defence assessment — 270 estimate —
8 Facilities, environmental and works approvals referral only if triggered
Approvals for the bases, ranges, wharves and infrastructure the capability requires.
Triggered when: The capability requires new or modified facilities, which for a major platform it invariably does.
Department of Climate Change, Energy, the Environment and Water assessment — 400 estimate —
9 Design, build and delivery application — applicant — 2555 estimate —
10 Test, evaluation and acceptance into service certification Department of Defence assessment — 540 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

The same body asked more than once

Sources

  1. Department of Defence, Capability Life Cycle and Integrated Investment Program
  2. ANAO, Capability Development Reform, and related Defence performance audits finding governance arrangements were not implemented effectively
  3. Department of Defence, Rebuilding Defence Capability, 2 July 2026, establishing the Defence Delivery Agency from 1 July 2027
  4. Rebuilding Defence Capability: An Independent Report, Department of Defence, July 2026, https://www.defence.gov.au/sites/default/files/2026-07/RebuildingDefenceCapability_FINAL.pdf, accessed 2026-11-09
  5. Going to the Next Level: the report of the Defence Procurement and Sustainment Review (Mortimer Review), Defence Materiel Organisation, 2008, http://repository.jeffmalone.org/files/defence/mortimerReview.pdf, accessed 2026-11-09
  6. Planning and Approval of Defence Major Capital Equipment Projects, ANAO Audit Report No. 48 2008-09, https://www.anao.gov.au/sites/default/files/ANAO_Report_2008-2009_48.pdf, accessed 2026-11-09