Acquire a major defence capability
Years of analysis and gates before a contract is signed, none of it on a statutory clock, none of it with published elapsed times, and none of it reviewable by anyone outside Defence.
longest dependent chain
across 2 bodies
scheduling or queue, not assessment
vs. 5540 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 2555d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 2445d | Someone is genuinely evaluating the merits. | |
| scheduling | 540d | Waiting for a person or committee to become available. |
540 of 5540 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A capability need is identified that requires government approval and a major acquisition contract.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 | Capability need identified and entered in the investment program application | Department of Defence | assessment | — | 365 estimate | — |
| 2 |
Gate 0: strategy and concepts
decision
Internal endorsement that the need is real and warrants development. after
Capability need identified and entered in the investment program 4995d slack
|
Department of Defence | scheduling | — | 180 estimate | — |
| 3 |
Risk mitigation and requirement setting
assessment
Options analysis, industry engagement, cost and schedule estimation, and requirements definition. after
Gate 0: strategy and concepts 4265d slack
|
Department of Defence | assessment | — | 730 estimate | — |
| 4 |
Gate 1: government first pass approval
decision
Government approves the options to be developed and the funding to develop them. after
Risk mitigation and requirement setting 4085d slack
|
Department of Defence | scheduling | — | 180 estimate | — |
| 5 |
Solicitation and tender evaluation
assessment
after
Gate 1: government first pass approval 3545d slack
|
Department of Defence | assessment | — | 540 estimate | — |
| 6 |
Gate 2: government second pass approval
decision
Government approves the acquisition and the funding. after
Solicitation and tender evaluation 3365d slack
|
Department of Defence | scheduling | — | 180 estimate | — |
| 7 |
Contract negotiation and execution
decision
after
Gate 2: government second pass approval 3095d slack
|
Department of Defence | assessment | — | 270 estimate | — |
| 8 |
Facilities, environmental and works approvals
referral
only if triggered Approvals for the bases, ranges, wharves and infrastructure the capability requires. Triggered when: The capability requires new or modified facilities, which for a major platform it invariably does. after
Gate 2: government second pass approval 2965d slack
|
Department of Climate Change, Energy, the Environment and Water | assessment | — | 400 estimate | — |
| 9 |
Design, build and delivery
application
after
Contract negotiation and execution 540d slack
|
— | applicant | — | 2555 estimate | — |
| 10 | Test, evaluation and acceptance into service certification | Department of Defence | assessment | — | 540 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
Steps that may not need to wait
- Facilities, environmental and works approvals is a referral queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?
The same body asked more than once
- defence (assessment) appears at Risk mitigation and requirement setting, Solicitation and tender evaluation. Could these be a single sign-off?
Sources
- Department of Defence, Capability Life Cycle and Integrated Investment Program
- ANAO, Capability Development Reform, and related Defence performance audits finding governance arrangements were not implemented effectively
- Department of Defence, Rebuilding Defence Capability, 2 July 2026, establishing the Defence Delivery Agency from 1 July 2027
- Rebuilding Defence Capability: An Independent Report, Department of Defence, July 2026, https://www.defence.gov.au/sites/default/files/2026-07/RebuildingDefenceCapability_FINAL.pdf, accessed 2026-11-09
- Going to the Next Level: the report of the Defence Procurement and Sustainment Review (Mortimer Review), Defence Materiel Organisation, 2008, http://repository.jeffmalone.org/files/defence/mortimerReview.pdf, accessed 2026-11-09
- Planning and Approval of Defence Major Capital Equipment Projects, ANAO Audit Report No. 48 2008-09, https://www.anao.gov.au/sites/default/files/ANAO_Report_2008-2009_48.pdf, accessed 2026-11-09
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-defence-major-acquisition.toml and open a pull request, or
send us the correction.