Environmental and planning approval for high speed rail — Newcastle to Sydney

One railway, two complete environmental assessments, on two clocks, to two decision-makers, under two sets of requirements — with the Commonwealth as proponent on one side and approver on the other.

infrastructure194 km of new dedicated high speed rail, roughly 115 km in tunnel, four stations, crossing many local government areas skeleton compare across jurisdictions
2700 days elapsed
longest dependent chain
15 discrete steps
across 3 bodies
0% waiting on availability
scheduling or queue, not assessment
490 days saved by concurrency
vs. 3190 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 1275d Waiting on the applicant to supply or fix something.
third party 1080d Waiting on an external body outside the regulator's control.
assessment 300d Someone is genuinely evaluating the merits.
statutory 45d A legislated period that must elapse regardless of readiness.

The process, step by step

Applies when: A Commonwealth agency proposes linear infrastructure crossing state land that triggers both the EPBC Act and the NSW critical state significant infrastructure pathway.

#StepWhoWhy it waits ClockTypicalBasis
1 Development phase: route definition and reference design application
Two year phase funded in February 2026 to take the route to a design that can be assessed and costed.
High Speed Rail Authority applicant — 730 reported —
2 Geotechnical, biodiversity and heritage field investigation assessment
Survey along a 194 km corridor, including seasonal ecological survey windows and Aboriginal cultural heritage assessment.
High Speed Rail Authority third party — 540 estimate —
3 Refer the action under the EPBC Act application Department of Climate Change, Energy, the Environment and Water applicant — 10 estimate EPBC Act 1999 (Cth), s 68
4 Controlled action decision decision Department of Climate Change, Energy, the Environment and Water assessment 28 40 legislated EPBC Act 1999 (Cth), s 75
5 Secretary's environmental assessment requirements (NSW) referral
NSW sets what the environmental impact statement must address, after consulting agencies and councils.
NSW Department of Planning, Housing and Infrastructure assessment — 90 estimate Environmental Planning and Assessment Act 1979 (NSW), Division 5.2
6 Prepare the NSW environmental impact statement application High Speed Rail Authority applicant — 365 estimate —
7 Prepare Commonwealth assessment documentation application
Documentation addressing the Commonwealth guidelines for the matters protected under the EPBC Act.
after Controlled action decision 1140d slack
High Speed Rail Authority applicant — 240 estimate —
8 Public exhibition of the environmental impact statement (NSW) notification NSW Department of Planning, Housing and Infrastructure statutory 28 45 estimate —
9 Commonwealth public comment period notification Department of Climate Change, Energy, the Environment and Water statutory 20 20 legislated EPBC Act 1999 (Cth), ss 93-95
10 Submissions report and amendment report application
Respond to every submission received on a corridor crossing many communities.
High Speed Rail Authority applicant — 180 estimate —
11 NSW assessment report assessment NSW Department of Planning, Housing and Infrastructure assessment — 150 estimate —
12 Commonwealth recommendation report assessment Department of Climate Change, Energy, the Environment and Water queue — 120 estimate EPBC Act 1999 (Cth), s 100
13 NSW infrastructure approval decision
after NSW assessment report 540d slack
NSW Department of Planning, Housing and Infrastructure assessment — 60 estimate Environmental Planning and Assessment Act 1979 (NSW), s 5.19
14 Commonwealth approval and conditions decision Department of Climate Change, Energy, the Environment and Water assessment 56 60 legislated EPBC Act 1999 (Cth), s 133
15 Corridor acquisition registration
Acquire the land and interests the corridor requires, by agreement or compulsorily.
— third party — 540 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

Proposed changes

  • Publish and reuse ecological survey data instead of resurveying digitise ~180d
    The longest single delay in federal environmental approval happens before any application exists: waiting for the season in which a species can lawfully be surveyed. Survey data is collected at proponents' expense, submitted to government, and then not made usable by the next proponent on the next block.
  • One environmental impact statement for high speed rail, not two merge
    A Commonwealth agency building a Commonwealth priority prepares two environmental impact assessments of the same railway, runs two public comment periods with the affected communities, and waits on two decisions. On the database's own numbers this costs almost no calendar time — which is a more interesting finding than if it did.

Sources

  1. Environment Protection and Biodiversity Conservation Act 1999 (Cth)
  2. Environmental Planning and Assessment Act 1979 (NSW), Division 5.2
  3. Infrastructure Australia, Stage 3 Evaluation Report, High Speed Rail Sydney-Newcastle, November 2025
  4. Railway Gazette International, 'Newcastle-Sydney high speed railway moves into development phase', 3 March 2026
  5. AECOM, appointment as Environmental Planning and Assessment Advisor for the development phase, 25 August 2026