A container terminal is approved at an Australian port

State planning, EPBC assessment and a sea dumping permit, running largely in parallel, with no queue or scheduling time anywhere in the model. This process is here because it is not the reason there is no container terminal at Newcastle.

infrastructureOne new container terminal and its associated capital dredging at an existing port skeleton compare across jurisdictions
540 days elapsed
longest dependent chain
6 discrete steps
across 2 bodies
0% waiting on availability
scheduling or queue, not assessment
758 days saved by concurrency
vs. 1298 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

assessment 540d Someone is genuinely evaluating the merits.

The process, step by step

Applies when: A port lessee seeks to develop container handling capacity requiring dredging and Commonwealth environmental approval.

#StepWhoWhy it waits ClockTypicalBasis
1 State planning approval assessment
State significant development or infrastructure assessment, including environmental impact statement and public exhibition.
NSW Department of Planning, Housing and Infrastructure assessment — 540 estimate —
2 EPBC referral and controlled action decision referral
Whether the proposal is a controlled action requiring Commonwealth assessment.
Department of Climate Change, Energy, the Environment and Water statutory 28 28 legislated Environment Protection and Biodiversity Conservation Act 1999 (Cth)
3 EPBC assessment and approval assessment Department of Climate Change, Energy, the Environment and Water assessment — 365 estimate Environment Protection and Biodiversity Conservation Act 1999 (Cth)
4 Sea dumping permit for dredge spoil application
A separate Commonwealth permit, under a separate Act, for placing dredged material at sea.
Department of Climate Change, Energy, the Environment and Water assessment 90 365 p90 540d published Environment Protection (Sea Dumping) Act 1981 (Cth), s 19
5 Commercial preconditions satisfied decision
Whether the project can proceed on terms anybody will fund. Not a permit, not an assessment, and not visible to a process map.
— assessment — 0 reported —
6 Terminal approved and able to proceed decision — assessment — 0 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Proposed changes

Sources

  1. Environment Protection (Sea Dumping) Act 1981 (Cth), s 19: the Minister must grant or refuse a permit within 90 days after the application is made, extended where Subdivision A of Division 4 of Part 11 of the EPBC Act applies
  2. DCCEEW: sea dumping applications may take over 12 months to be assessed depending on their complexity
  3. Environment Protection and Biodiversity Conservation Act 1999 (Cth)
  4. Port of Brisbane Channel Enhancement Project: dredging could start in 2028 and would require a Commonwealth sea dumping permit if material is placed outside internal state waters
  5. Port of Newcastle 10-year maintenance sea dumping permit renewed September 2022, running to 31 July 2032