Build a major transmission line — concurrent easement pathway (Victoria)
Identical to the sequential pathway except for one dependency edge. Victoria removed it in 2026, explicitly because the sequence was delaying VNI West and the Western Renewables Link. This is the rare case where the reform this database would propose has already been enacted and can be measured.
longest dependent chain
across 5 bodies
scheduling or queue, not assessment
vs. 4215 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| assessment | 1215d | Someone is genuinely evaluating the merits. | |
|---|---|---|---|
| applicant | 900d | Waiting on the applicant to supply or fix something. | |
| third party | 540d | Waiting on an external body outside the regulator's control. | |
| statutory | 300d | A legislated period that must elapse regardless of readiness. |
The process, step by step
Applies when: An actionable ISP project in Victoria, following the 2026 amendments permitting compulsory easement acquisition to proceed concurrently with the environment effects process.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 | Identified as an actionable project in the Integrated System Plan assessment | Australian Energy Market Operator | assessment | — | 365 estimate | — |
| 2 |
Project specification consultation report and consultation
notification
after
Identified as an actionable project in the Integrated System Plan 2470d slack
|
Transmission network service provider | statutory | — | 120 estimate | National Electricity Rules, rule 5.15A |
| 3 |
Project assessment draft report and consultation
notification
after
Project specification consultation report and consultation 2290d slack
|
Transmission network service provider | statutory | — | 180 estimate | National Electricity Rules, rule 5.15A |
| 4 |
Project assessment conclusions report
decision
after
Project assessment draft report and consultation 2170d slack
|
Transmission network service provider | assessment | — | 120 estimate | National Electricity Rules, rule 5.15A |
| 5 |
Contingent project application and revenue determination
decision
after
Project assessment conclusions report 1990d slack
|
Australian Energy Regulator | assessment | — | 180 estimate | National Electricity Rules, Chapter 6A |
| 6 |
Route selection and landholder engagement
application
after
Project assessment conclusions report 1630d slack
|
Transmission network service provider | third party | — | 540 estimate | — |
| 7 |
Commonwealth environmental approval
decision
after
Route selection and landholder engagement 1090d slack
|
Department of Climate Change, Energy, the Environment and Water | assessment | — | 540 estimate | Environment Protection and Biodiversity Conservation Act 1999 (Cth) |
| 8 |
Environment effects statement and assessment
decision
Scoping, technical reference group, exhibition, inquiry panel and the Minister's assessment. after
Route selection and landholder engagement 900d slack
|
Victorian Minister for Planning (Environment Effects Statement) | assessment | — | 730 estimate | Environment Effects Act 1978 (Vic) |
| 9 |
Easement acquisition, concurrent with assessment
registration
Acquisition proceeds alongside the environment effects process rather than after it. after
Route selection and landholder engagement 1090d slack
|
Transmission network service provider | third party | — | 540 legislated | Electricity Industry Act 2000 (Vic), as amended 2026 |
| 10 | Construction and commissioning application | Transmission network service provider | applicant | — | 900 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
Steps that may not need to wait
- Project specification consultation report and consultation is a notification queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?
Proposed changes
-
Assess once under an accredited state process, decide twice
merge
~150d Where a project needs both state and Commonwealth environmental approval, two documents are prepared, two consultations are run and two assessments are performed on the same impacts. Assessment bilateral agreements already allow one assessment to serve both decisions — they are simply not in place for most of the country.
Sources
- Amendments to the Electricity Industry Act 2000 (Vic), 2026, permitting concurrent easement acquisition and environment effects assessment
- Environment Effects Act 1978 (Vic)
- National Electricity Rules, rule 5.15A
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/vic-transmission-line.toml and open a pull request, or
send us the correction.