Build a major transmission line — concurrent easement pathway (Victoria)

Identical to the sequential pathway except for one dependency edge. Victoria removed it in 2026, explicitly because the sequence was delaying VNI West and the Western Renewables Link. This is the rare case where the reform this database would propose has already been enacted and can be measured.

energyA multi-hundred-kilometre high voltage transmission line designated actionable in the Integrated System Plan, crossing private agricultural land skeleton compare across jurisdictions
2955 days elapsed
longest dependent chain
10 discrete steps
across 5 bodies
0% waiting on availability
scheduling or queue, not assessment
1260 days saved by concurrency
vs. 4215 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

assessment 1215d Someone is genuinely evaluating the merits.
applicant 900d Waiting on the applicant to supply or fix something.
third party 540d Waiting on an external body outside the regulator's control.
statutory 300d A legislated period that must elapse regardless of readiness.

The process, step by step

Applies when: An actionable ISP project in Victoria, following the 2026 amendments permitting compulsory easement acquisition to proceed concurrently with the environment effects process.

#StepWhoWhy it waits ClockTypicalBasis
1 Identified as an actionable project in the Integrated System Plan assessment Australian Energy Market Operator assessment — 365 estimate —
2 Project specification consultation report and consultation notification Transmission network service provider statutory — 120 estimate National Electricity Rules, rule 5.15A
3 Project assessment draft report and consultation notification Transmission network service provider statutory — 180 estimate National Electricity Rules, rule 5.15A
4 Project assessment conclusions report decision Transmission network service provider assessment — 120 estimate National Electricity Rules, rule 5.15A
5 Contingent project application and revenue determination decision Australian Energy Regulator assessment — 180 estimate National Electricity Rules, Chapter 6A
6 Route selection and landholder engagement application Transmission network service provider third party — 540 estimate —
7 Commonwealth environmental approval decision Department of Climate Change, Energy, the Environment and Water assessment — 540 estimate Environment Protection and Biodiversity Conservation Act 1999 (Cth)
8 Environment effects statement and assessment decision
Scoping, technical reference group, exhibition, inquiry panel and the Minister's assessment.
Victorian Minister for Planning (Environment Effects Statement) assessment — 730 estimate Environment Effects Act 1978 (Vic)
9 Easement acquisition, concurrent with assessment registration
Acquisition proceeds alongside the environment effects process rather than after it.
Transmission network service provider third party — 540 legislated Electricity Industry Act 2000 (Vic), as amended 2026
10 Construction and commissioning application Transmission network service provider applicant — 900 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

Proposed changes

  • Assess once under an accredited state process, decide twice merge ~150d
    Where a project needs both state and Commonwealth environmental approval, two documents are prepared, two consultations are run and two assessments are performed on the same impacts. Assessment bilateral agreements already allow one assessment to serve both decisions — they are simply not in place for most of the country.

Sources

  1. Amendments to the Electricity Industry Act 2000 (Vic), 2026, permitting concurrent easement acquisition and environment effects assessment
  2. Environment Effects Act 1978 (Vic)
  3. National Electricity Rules, rule 5.15A