A water infrastructure project reaches construction funding
Three business cases in series, each gating the next, then a construction commitment. The framework is sequenced the way this site would design it. What goes wrong happens outside the framework, before it starts.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 2720 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| assessment | 1810d | Someone is genuinely evaluating the merits. | |
|---|---|---|---|
| scheduling | 180d | Waiting for a person or committee to become available. |
180 of 1990 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A state or proponent seeks Commonwealth contribution to a water infrastructure project.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Feasibility or research study
assessment
Funded under the Science Program at up to 50 per cent or more where there is demonstrated need. |
National Water Grid Authority | assessment | — | 365 estimate | — |
| 2 |
Preliminary business case
assessment
Required before a detailed business case proposal can be made. after
Feasibility or research study 1260d slack
|
National Water Grid Authority | assessment | — | 365 published | — |
| 3 |
Detailed business case
assessment
Required before a construction proposal can be made. This is the gate. after
Preliminary business case 720d slack
|
National Water Grid Authority | assessment | — | 540 published | — |
| 4 |
Commonwealth construction funding commitment
decision
Up to 50 per cent of total capital costs. Committed through the Budget, on an annual cycle. after
Detailed business case 540d slack
|
National Water Grid Authority | scheduling | — | 180 estimate | — |
| 5 |
State planning and environmental approval
assessment
State assessment of the dam, weir or pipeline and its inundation footprint.
|
— | assessment | — | 540 estimate | — |
| 6 |
EPBC assessment and approval
assessment
after
Commonwealth construction funding commitment 175d slack
|
Department of Climate Change, Energy, the Environment and Water | assessment | — | 365 estimate | Environment Protection and Biodiversity Conservation Act 1999 (Cth) |
| 7 |
Water entitlement secured for the project
certification
A dam is a container. The water that goes in it has to come from somewhere, and in most Australian systems it is already spoken for. after
Commonwealth construction funding commitment 175d slack
|
State water authority and register | third party | — | 365 reported | — |
| 8 | Construction may commence decision | — | assessment | — | 0 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- national-water-grid (assessment) appears at Feasibility or research study, Preliminary business case, Detailed business case. Could these be a single sign-off?
Proposed changes
-
Storage is a container, and in a capped system the water in it already belongs to somebody
threshold
Many Australian water systems were fully or over allocated by the 1980s. A new dam in a capped system buys reliability, not volume — a real benefit, and a much smaller one than a gigalitre figure implies.
-
61 projects, up to $10 billion, 23 published business cases
digitise
The National Water Grid Investment Framework requires a detailed business case before a construction proposal. Dungowan Dam had $595 million committed over seven years and was cancelled because the business case did not support construction. The framework was never the problem.
Sources
- National Water Grid Investment Framework: staged funding for feasibility/research studies, preliminary business case, detailed business case and construction, with up to 50 per cent Commonwealth contribution at each stage
- A preliminary business case is required to support detailed business case proposals; a detailed business case is required to support construction proposals
- The National Water Grid Fund portfolio of 61 large water projects has a total capital cost estimate of up to $10 billion, with only 23 having publicly available business cases
- Environment Protection and Biodiversity Conservation Act 1999 (Cth)
- Murray-Darling Basin Plan 2012: Sustainable Diversion Limits, replacing the Murray-Darling Cap introduced in June 1995
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-water-infrastructure-funding.toml and open a pull request, or
send us the correction.