Raw Aus Pol

Simple Wins / Australian Red Tape Every step, every clock, every authority -- written down.

Build a block of townhouses — New South Wales

Scale changes the process qualitatively: mandatory public notification, multiple referrals, panel determination, development contributions and a subdivision that cannot start until the works are done.

developmentMulti-dwelling housing, roughly 5 to 20 dwellings, site already held skeleton compare across jurisdictions
480 days elapsed
longest dependent chain
16 discrete steps
across 3 bodies
38% waiting on availability
scheduling or queue, not assessment
42 days saved by concurrency
vs. 522 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 154d Waiting on the applicant to supply or fix something.
assessment 145d Someone is genuinely evaluating the merits.
queue 134d Waiting behind unrelated work in a backlog.
scheduling 47d Waiting for a person or committee to become available.

181 of 480 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: Multi-dwelling housing permitted with consent in the applicable zone, on a site the developer already controls.

#StepWhoWhy it waits ClockTypicalBasis
1 Prepare design and consultant documentation application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation.
— applicant — 150 estimate —
2 Lodge the development application application Consent authority (NSW council) applicant — 3 published Environmental Planning and Assessment Act 1979 (NSW)
3 Pay the assessment fee fee Consent authority (NSW council) applicant — 1 estimate —
4 Lodgement and properly-made check assessment
The authority checks the application is complete before assessment begins.
after Pay the assessment fee 312d slack
Consent authority (NSW council) queue — 14 estimate —
5 Public notification and submissions notification Consent authority (NSW council) statutory 28 28 estimate —
6 Internal and external referrals referral
Traffic, engineering, waste, landscape, heritage and state agency referrals, each responding separately.
Consent authority (NSW council) queue — 45 estimate —
7 Assessment against the planning rules assessment Consent authority (NSW council) assessment — 80 estimate Environmental Planning and Assessment Act 1979 (NSW)
8 Information request and amended plans assessment only if triggered
The clock commonly stops while the applicant answers questions.
Triggered when: The authority requests further information.
Consent authority (NSW council) applicant — 90 estimate —
9 Determination and issue of development consent decision Consent authority (NSW council) scheduling — 35 estimate Environmental Planning and Assessment Act 1979 (NSW)
10 Third party appeal period appeal only if triggered
A legislated window in which a submitter may seek review of the decision.
Triggered when: Submissions were received and a submitter has standing to seek review.
— statutory 28 28 estimate —
11 Pay development contributions fee Consent authority (NSW council) applicant — 14 estimate —
12 Obtain the construction certificate certification
Certifies that construction documentation complies with the National Construction Code and the planning approval.
Registered certifier (NSW) assessment — 40 estimate Environmental Planning and Assessment Act 1979 (NSW)
13 Mandatory inspections during construction inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time.
Registered certifier (NSW) scheduling — 12 estimate —
14 Obtain the occupation certificate certification
Authorises the building to be occupied.
Registered certifier (NSW) assessment — 25 estimate —
15 Obtain the subdivision certificate certification
Authorises registration of the plan creating separate titles. Cannot begin until the works are complete and certified.
Consent authority (NSW council) queue — 45 estimate —
16 Register the plan of subdivision registration
The land registry records the plan and issues the new titles.
NSW Land Registry Services queue — 30 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

The same body asked more than once

Proposed changes

Sources

  1. New South Wales published development assessment and building approval guidance, accessed 2026-08-30

Something wrong here?

This page is wrong in some way -- every page like it is. If you have run this process, the most useful thing you can do is tell us which step took longer than we say and why. Edit data/processes/nsw-townhouses.toml and open a pull request, or send us the correction.