Build a block of townhouses — New South Wales
Scale changes the process qualitatively: mandatory public notification, multiple referrals, panel determination, development contributions and a subdivision that cannot start until the works are done.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 522 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 154d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 145d | Someone is genuinely evaluating the merits. | |
| queue | 134d | Waiting behind unrelated work in a backlog. | |
| scheduling | 47d | Waiting for a person or committee to become available. |
181 of 480 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: Multi-dwelling housing permitted with consent in the applicable zone, on a site the developer already controls.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Prepare design and consultant documentation
application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation. |
— | applicant | — | 150 estimate | — |
| 2 |
Lodge the development application
application
after
Prepare design and consultant documentation 327d slack
|
Consent authority (NSW council) | applicant | — | 3 published | Environmental Planning and Assessment Act 1979 (NSW) |
| 3 |
Pay the assessment fee
fee
after
Lodge the development application 326d slack
|
Consent authority (NSW council) | applicant | — | 1 estimate | — |
| 4 |
Lodgement and properly-made check
assessment
The authority checks the application is complete before assessment begins. after
Pay the assessment fee 312d slack
|
Consent authority (NSW council) | queue | — | 14 estimate | — |
| 5 |
Public notification and submissions
notification
after
Lodgement and properly-made check 284d slack
|
Consent authority (NSW council) | statutory | 28 | 28 estimate | — |
| 6 |
Internal and external referrals
referral
Traffic, engineering, waste, landscape, heritage and state agency referrals, each responding separately. after
Lodgement and properly-made check 267d slack
|
Consent authority (NSW council) | queue | — | 45 estimate | — |
| 7 | Assessment against the planning rules assessment | Consent authority (NSW council) | assessment | — | 80 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 8 |
Information request and amended plans
assessment
only if triggered The clock commonly stops while the applicant answers questions. Triggered when: The authority requests further information. after
Assessment against the planning rules 97d slack
|
Consent authority (NSW council) | applicant | — | 90 estimate | — |
| 9 |
Determination and issue of development consent
decision
after
Assessment against the planning rules 152d slack
|
Consent authority (NSW council) | scheduling | — | 35 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 10 |
Third party appeal period
appeal
only if triggered A legislated window in which a submitter may seek review of the decision. Triggered when: Submissions were received and a submitter has standing to seek review. after
Determination and issue of development consent 124d slack
|
— | statutory | 28 | 28 estimate | — |
| 11 |
Pay development contributions
fee
after
Determination and issue of development consent 138d slack
|
Consent authority (NSW council) | applicant | — | 14 estimate | — |
| 12 |
Obtain the construction certificate
certification
Certifies that construction documentation complies with the National Construction Code and the planning approval. after
Determination and issue of development consent 112d slack
|
Registered certifier (NSW) | assessment | — | 40 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 13 |
Mandatory inspections during construction
inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time. after
Obtain the construction certificate 100d slack
|
Registered certifier (NSW) | scheduling | — | 12 estimate | — |
| 14 |
Obtain the occupation certificate
certification
Authorises the building to be occupied. after
Mandatory inspections during construction 75d slack
|
Registered certifier (NSW) | assessment | — | 25 estimate | — |
| 15 |
Obtain the subdivision certificate
certification
Authorises registration of the plan creating separate titles. Cannot begin until the works are complete and certified. after
Obtain the occupation certificate 30d slack
|
Consent authority (NSW council) | queue | — | 45 estimate | — |
| 16 |
Register the plan of subdivision
registration
The land registry records the plan and issues the new titles.
|
NSW Land Registry Services | queue | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- nsw-council-consent (assessment) appears at Lodgement and properly-made check, Assessment against the planning rules, Information request and amended plans. Could these be a single sign-off?
- nsw-private-certifier (certification) appears at Obtain the construction certificate, Obtain the occupation certificate. Could these be a single sign-off?
Proposed changes
-
Run internal council referrals concurrently and publish their queue times
parallelise
~25d Traffic, engineering, waste, landscape and heritage teams assess different things and rarely depend on each other's findings, yet are commonly worked through in sequence.
-
Bring the subdivision certificate check forward to practical completion
resequence
~30d Most of what is checked at subdivision certificate stage is knowable before the last works are finished, but the check begins only afterwards -- at the point of maximum holding cost.
-
Determine panel matters on a rolling basis rather than a monthly agenda
resequence
~21d Where assessment is complete and no submissions are contested, allow determination without waiting for the next scheduled panel meeting.
Sources
- New South Wales published development assessment and building approval guidance, accessed 2026-08-30
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/nsw-townhouses.toml and open a pull request, or
send us the correction.