Build a single house — NSW, complying development certificate

The fast path for the same physical house: a registered certifier checks the design against fixed codes and issues a certificate. No merit assessment, no neighbour submissions, no determination meeting.

developmentSingle detached dwelling on an existing lot draft compare across jurisdictions
79 days elapsed
longest dependent chain
7 discrete steps
across 1 bodies
6% waiting on availability
scheduling or queue, not assessment
2 days saved by concurrency
vs. 81 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

assessment 34d Someone is genuinely evaluating the merits.
applicant 33d Waiting on the applicant to supply or fix something.
statutory 7d A legislated period that must elapse regardless of readiness.
scheduling 5d Waiting for a person or committee to become available.

5 of 79 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: The proposal meets every standard in the complying development codes and the land is not excluded from the pathway.

#StepWhoWhy it waits ClockTypicalBasis
1 Prepare plans to the code application
Design must comply with every applicable development standard; a single non-compliance sends the project back to the merit pathway.
— applicant — 30 estimate —
2 Engage a registered certifier application
Any registered certifier may be engaged. This is the structural difference from the DA pathway: a market rather than a single queue.
after Prepare plans to the code 46d slack
Registered certifier (NSW) applicant — 3 estimate —
3 Notice to neighbours before work starts notification
After the certificate is issued, neighbours within 20 metres of the lot boundary are given written notice before any work commences. There is no submission period that can alter the outcome.
Registered certifier (NSW) statutory 7 7 published —
4 Assessment against the codes and issue of the certificate certification
A compliance check against fixed standards rather than a judgement on the merits.
Registered certifier (NSW) assessment 20 24 published Environmental Planning and Assessment Act 1979 (NSW)
5 Appoint principal certifier application Registered certifier (NSW) applicant — 2 estimate —
6 Mandatory critical stage inspections inspection Registered certifier (NSW) scheduling — 5 estimate —
7 Occupation certificate certification Registered certifier (NSW) assessment — 10 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

The same body asked more than once

Sources

  1. State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 (NSW) — structure of the pathway
  2. Planning performance (complying development certificates, Dwelling House (CDC) average assessment days), NSW Department of Planning, Housing and Infrastructure, https://www.planning.nsw.gov.au/data-and-resources/planning-performance, accessed 2026-11-09
  3. Complying development (updated 26 June 2026), NSW Department of Planning, Housing and Infrastructure, https://www.planning.nsw.gov.au/the-planning-system/development-assessment/planning-approval-pathways/complying-development, accessed 2026-11-09
  4. What to tell your neighbours (updated 23 March 2026), NSW Department of Planning, Housing and Infrastructure, https://www.planning.nsw.gov.au/the-planning-system/development-assessment/planning-approval-pathways/complying-development/what-to-tell-your-neighbours, accessed 2026-11-09