Open a long day care centre — New South Wales
Three tiers of government, each with a gate. The Commonwealth expanded demand on a fixed date; supply passes through a council development consent and two state approvals, on no particular timetable.
longest dependent chain
across 4 bodies
scheduling or queue, not assessment
vs. 1180 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 589d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 285d | Someone is genuinely evaluating the merits. | |
| queue | 60d | Waiting behind unrelated work in a backlog. | |
| scheduling | 45d | Waiting for a person or committee to become available. | |
| statutory | 21d | A legislated period that must elapse regardless of readiness. |
105 of 1000 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A provider seeks to build and operate a new centre-based education and care service.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Site selection, feasibility and design
application
Find a site that is zoned for the use, will fit the required indoor and outdoor space per place, and can be serviced by parking and access. |
— | applicant | — | 180 estimate | — |
| 2 |
Acoustic, traffic and plan of management reports
application
Noise assessment of children at play, traffic and parking assessment, and an operational plan of management. after
Site selection, feasibility and design 730d slack
|
— | applicant | — | 90 estimate | — |
| 3 |
Lodge the development application
application
after
Acoustic, traffic and plan of management reports 725d slack
|
Consent authority (NSW council) | applicant | — | 5 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 4 |
Neighbour notification and submissions
notification
after
Lodge the development application 704d slack
|
Consent authority (NSW council) | statutory | 14 | 21 estimate | — |
| 5 |
Council assessment
assessment
Assessment against the planning controls and the applicable child care planning guideline. after
Neighbour notification and submissions 584d slack
|
Consent authority (NSW council) | assessment | — | 120 estimate | — |
| 6 |
Determination
decision
after
Council assessment 539d slack
|
Consent authority (NSW council) | scheduling | — | 45 estimate | — |
| 7 |
Merits appeal to the Land and Environment Court
appeal
only if triggered Where consent is refused, the applicant may seek review on the merits. Triggered when: The application is refused, or deemed refused. after
Determination 239d slack
|
— | queue | — | 300 estimate | — |
| 8 |
Construction certificate
certification
after
Determination 494d slack
|
Registered certifier (NSW) | assessment | — | 45 estimate | — |
| 9 |
Construction and fit-out
application
after
Construction certificate 194d slack
|
— | applicant | — | 300 estimate | — |
| 10 |
Occupation certificate
certification
after
Construction and fit-out 164d slack
|
Registered certifier (NSW) | assessment | — | 30 estimate | — |
| 11 |
Provider approval
registration
Assessment of whether the provider is fit and proper to operate an education and care service. after
Determination 479d slack
|
NSW Early Childhood Education regulatory authority | assessment | 60 | 60 legislated | Education and Care Services National Law |
| 12 |
Service approval
registration
Assessment of the specific premises, including layout, space, fencing, and the nominated supervisor.
|
NSW Early Childhood Education regulatory authority | assessment | 90 | 90 legislated | Education and Care Services National Law |
| 13 |
Child Care Subsidy provider approval
registration
Commonwealth approval under Family Assistance Law so that families attending the service can receive the subsidy. after
Service approval 14d slack
|
Department of Education (Commonwealth) | queue | — | 60 estimate | A New Tax System (Family Assistance) (Administration) Act 1999 (Cth) |
| 14 |
Recruit qualified educators and an early childhood teacher
application
Meet the qualification and ratio requirements, including the early childhood teacher requirement. after
Determination 419d slack
|
— | third party | — | 120 estimate | — |
| 15 | Open registration | — | applicant | — | 14 estimate | — |
| 16 |
Assessment and rating against the National Quality Standard
assessment
only if triggered The regulatory authority assesses and rates the operating service. Triggered when: Scheduled by the regulatory authority after the service commences operating. after
Open
|
NSW Early Childhood Education regulatory authority | queue | — | 365 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- nsw-private-certifier (certification) appears at Construction certificate, Occupation certificate. Could these be a single sign-off?
Proposed changes
-
Run service approval and Child Care Subsidy approval against the building, not after it
parallelise
~120d A finished, fitted-out, empty childcare centre carrying full finance waits 90 days for service approval and then 60 more for Commonwealth subsidy approval. Most of what both examine is knowable from the approved plans months earlier.
-
A code-assessable pathway for childcare centres that meet the planning guideline
threshold
~120d Nearly every contested childcare application answers the same three objections — noise, traffic, parking — through the same three consultant disciplines against published guidelines. Where the answers are that standardised, the assessment is already code-shaped.
Sources
- Education and Care Services National Law, provider and service approval provisions
- ACECQA, Guide to the National Quality Framework, applications and approvals
- State Environmental Planning Policy (Transport and Infrastructure) 2021 (NSW), education and child care provisions
- Department of Education (Cth), published guidance on the Child Care Subsidy approval process
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/nsw-childcare-centre.toml and open a pull request, or
send us the correction.