Build a multi storey apartment building via the Housing Delivery Authority — New South Wales

The same building as the council pathway, assessed by a different body under a different procedure. This is the closest thing Australian planning has to a controlled experiment, and it is running right now at scale.

developmentClass 2 residential apartment building meeting the capital investment threshold for declaration as state significant development skeleton compare across jurisdictions
1048 days elapsed
longest dependent chain
17 discrete steps
across 5 bodies
18% waiting on availability
scheduling or queue, not assessment
45 days saved by concurrency
vs. 1093 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 560d Waiting on the applicant to supply or fix something.
assessment 270d Someone is genuinely evaluating the merits.
scheduling 100d Waiting for a person or committee to become available.
queue 90d Waiting behind unrelated work in a backlog.
statutory 28d A legislated period that must elapse regardless of readiness.

190 of 1048 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A housing proposal above the capital investment threshold that the Minister has declared to be state significant development on the recommendation of the Housing Delivery Authority.

#StepWhoWhy it waits ClockTypicalBasis
1 Expression of interest to the Housing Delivery Authority application
The proponent asks to be moved out of the council pathway.
Housing Delivery Authority (NSW) applicant — 30 estimate —
2 Housing Delivery Authority considers the proposal assessment
A panel of senior officials considers proposals in batches and recommends declaration.
Housing Delivery Authority (NSW) scheduling — 45 estimate —
3 Ministerial declaration as state significant development decision Housing Delivery Authority (NSW) scheduling — 30 estimate State Environmental Planning Policy (Planning Systems) 2021 (NSW)
4 Prepare design and consultant documentation application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation, plus a design statement.
— applicant — 300 estimate —
5 Secretary's environmental assessment requirements referral
The department sets what must be addressed, after consulting the council and the relevant agencies.
NSW Department of Planning, Housing and Infrastructure assessment — 45 estimate —
6 Prepare the environmental impact statement application — applicant — 150 estimate —
7 Lodge the application application NSW Department of Planning, Housing and Infrastructure applicant — 5 estimate —
8 Public exhibition notification
after Lodge the application 460d slack
NSW Department of Planning, Housing and Infrastructure statutory 28 28 estimate —
9 Response to submissions application
after Public exhibition 415d slack
— applicant — 45 estimate —
10 Departmental assessment assessment
One body assesses against the planning rules, having already gathered agency advice through the assessment requirements.
after Response to submissions 295d slack
NSW Department of Planning, Housing and Infrastructure assessment — 120 estimate —
11 Determination decision
after Departmental assessment 265d slack
NSW Department of Planning, Housing and Infrastructure assessment — 30 estimate Environmental Planning and Assessment Act 1979 (NSW), s 4.38
12 Obtain the construction certificate certification
after Determination 190d slack
Registered certifier (NSW) assessment — 75 estimate Environmental Planning and Assessment Act 1979 (NSW)
13 Lodge regulated designs and compliance declarations certification Registered certifier (NSW) applicant — 30 published Design and Building Practitioners Act 2020 (NSW)
14 Mandatory inspections during construction inspection Registered certifier (NSW) scheduling — 25 estimate —
15 Obtain the occupation certificate certification Registered certifier (NSW) assessment — 45 estimate —
16 Obtain the strata certificate certification
Strata certification returns to the council regardless of who granted consent.
Consent authority (NSW council) queue — 60 estimate —
17 Register the plan of strata registration NSW Land Registry Services queue — 30 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

Steps that may not need to wait

The same body asked more than once

Proposed changes

Sources

  1. Environmental Planning and Assessment Act 1979 (NSW), Division 4.7
  2. NSW Department of Planning, Housing and Infrastructure, published Housing Delivery Authority meeting outcomes, 2025-2026
  3. State Environmental Planning Policy (Planning Systems) 2021 (NSW)