Build a multi storey apartment building via the Housing Delivery Authority — New South Wales
The same building as the council pathway, assessed by a different body under a different procedure. This is the closest thing Australian planning has to a controlled experiment, and it is running right now at scale.
longest dependent chain
across 5 bodies
scheduling or queue, not assessment
vs. 1093 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 560d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 270d | Someone is genuinely evaluating the merits. | |
| scheduling | 100d | Waiting for a person or committee to become available. | |
| queue | 90d | Waiting behind unrelated work in a backlog. | |
| statutory | 28d | A legislated period that must elapse regardless of readiness. |
190 of 1048 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A housing proposal above the capital investment threshold that the Minister has declared to be state significant development on the recommendation of the Housing Delivery Authority.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Expression of interest to the Housing Delivery Authority
application
The proponent asks to be moved out of the council pathway. |
Housing Delivery Authority (NSW) | applicant | — | 30 estimate | — |
| 2 |
Housing Delivery Authority considers the proposal
assessment
A panel of senior officials considers proposals in batches and recommends declaration. after
Expression of interest to the Housing Delivery Authority 973d slack
|
Housing Delivery Authority (NSW) | scheduling | — | 45 estimate | — |
| 3 |
Ministerial declaration as state significant development
decision
after
Housing Delivery Authority considers the proposal 943d slack
|
Housing Delivery Authority (NSW) | scheduling | — | 30 estimate | State Environmental Planning Policy (Planning Systems) 2021 (NSW) |
| 4 |
Prepare design and consultant documentation
application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation, plus a design statement. after
Ministerial declaration as state significant development 643d slack
|
— | applicant | — | 300 estimate | — |
| 5 |
Secretary's environmental assessment requirements
referral
The department sets what must be addressed, after consulting the council and the relevant agencies. after
Ministerial declaration as state significant development 898d slack
|
NSW Department of Planning, Housing and Infrastructure | assessment | — | 45 estimate | — |
| 6 | Prepare the environmental impact statement application | — | applicant | — | 150 estimate | — |
| 7 |
Lodge the application
application
after
Prepare the environmental impact statement 488d slack
|
NSW Department of Planning, Housing and Infrastructure | applicant | — | 5 estimate | — |
| 8 |
Public exhibition
notification
after
Lodge the application 460d slack
|
NSW Department of Planning, Housing and Infrastructure | statutory | 28 | 28 estimate | — |
| 9 |
Response to submissions
application
after
Public exhibition 415d slack
|
— | applicant | — | 45 estimate | — |
| 10 |
Departmental assessment
assessment
One body assesses against the planning rules, having already gathered agency advice through the assessment requirements. after
Response to submissions 295d slack
|
NSW Department of Planning, Housing and Infrastructure | assessment | — | 120 estimate | — |
| 11 |
Determination
decision
after
Departmental assessment 265d slack
|
NSW Department of Planning, Housing and Infrastructure | assessment | — | 30 estimate | Environmental Planning and Assessment Act 1979 (NSW), s 4.38 |
| 12 |
Obtain the construction certificate
certification
after
Determination 190d slack
|
Registered certifier (NSW) | assessment | — | 75 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 13 |
Lodge regulated designs and compliance declarations
certification
after
Obtain the construction certificate 160d slack
|
Registered certifier (NSW) | applicant | — | 30 published | Design and Building Practitioners Act 2020 (NSW) |
| 14 |
Mandatory inspections during construction
inspection
after
Lodge regulated designs and compliance declarations 135d slack
|
Registered certifier (NSW) | scheduling | — | 25 estimate | — |
| 15 |
Obtain the occupation certificate
certification
after
Mandatory inspections during construction 90d slack
|
Registered certifier (NSW) | assessment | — | 45 estimate | — |
| 16 |
Obtain the strata certificate
certification
Strata certification returns to the council regardless of who granted consent. after
Obtain the occupation certificate 30d slack
|
Consent authority (NSW council) | queue | — | 60 estimate | — |
| 17 | Register the plan of strata registration | NSW Land Registry Services | queue | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
Steps that may not need to wait
- Secretary's environmental assessment requirements is a referral queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?
The same body asked more than once
- nsw-private-certifier (certification) appears at Obtain the construction certificate, Lodge regulated designs and compliance declarations, Obtain the occupation certificate. Could these be a single sign-off?
Proposed changes
-
Enter the fast pathway by meeting published criteria, not by being selected into it
threshold
~75d Both major fast-track housing pathways in Australia are entered by ministerial declaration on a panel's recommendation. A proponent cannot know in advance whether they qualify, cannot appeal exclusion, and waits on a meeting cycle to find out.
Sources
- Environmental Planning and Assessment Act 1979 (NSW), Division 4.7
- NSW Department of Planning, Housing and Infrastructure, published Housing Delivery Authority meeting outcomes, 2025-2026
- State Environmental Planning Policy (Planning Systems) 2021 (NSW)
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/nsw-apartments-hda.toml and open a pull request, or
send us the correction.