Build and open a residential aged care home — New South Wales

The same three-tier shape as childcare, with one difference that dominates everything else: the process is not what is stopping these being built. The economics are.

aged-careA new residential aged care home of about 120 places, developed by an existing registered provider skeleton compare across jurisdictions
1581 days elapsed
longest dependent chain
12 discrete steps
across 3 bodies
5% waiting on availability
scheduling or queue, not assessment
240 days saved by concurrency
vs. 1821 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 1155d Waiting on the applicant to supply or fix something.
assessment 330d Someone is genuinely evaluating the merits.
scheduling 75d Waiting for a person or committee to become available.
statutory 21d A legislated period that must elapse regardless of readiness.

75 of 1581 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A provider seeks to build and operate a new residential aged care home.

#StepWhoWhy it waits ClockTypicalBasis
1 Site selection and financial feasibility application
Identify a site, model the accommodation payment and subsidy revenue against construction and operating cost.
— applicant — 270 estimate —
2 Design and consultant documentation application
Architectural documentation meeting the aged care design and accommodation requirements, plus traffic, acoustic and access reports.
— applicant — 240 estimate —
3 Lodge the development application application Consent authority (NSW council) applicant — 5 estimate Environmental Planning and Assessment Act 1979 (NSW)
4 Neighbour notification and submissions notification Consent authority (NSW council) statutory 14 21 estimate —
5 Council assessment assessment Consent authority (NSW council) assessment — 150 estimate —
6 Determination decision
after Council assessment 850d slack
Consent authority (NSW council) scheduling — 45 estimate —
7 Construction certificate certification
after Determination 790d slack
Registered certifier (NSW) assessment — 60 estimate —
8 Construction and fit-out application
after Construction certificate 150d slack
— applicant — 640 estimate —
9 Occupation certificate certification
after Construction and fit-out 120d slack
Registered certifier (NSW) assessment — 30 estimate —
10 Provider registration, or variation to add the service registration
Registration in the applicable category under the Aged Care Act 2024, or a variation for an existing registered provider.
after Occupation certificate 30d slack
Aged Care Quality and Safety Commission assessment — 90 estimate Aged Care Act 2024 (Cth)
11 Recruit to the care minute and registered nurse requirements application
Staff to the sector-wide target of 215 care minutes per resident per day including 44 registered nurse minutes, and the 24/7 registered nurse requirement.
after Determination 610d slack
— third party — 240 reported —
12 Open and admit residents registration — scheduling — 30 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

The same body asked more than once

Proposed changes

  • Universal registration: one aged care approval instead of two merge ~90d
    The Aged Care Act 2024 merged provider approval and accreditation into a single registration in risk-based categories. It is the clearest counter-example to the assumption that merging approvals means weakening them — the same Act sharply increased the regulator's enforcement powers.

Sources

  1. Aged Care Act 2024 (Cth), commenced 1 November 2025, universal registration
  2. Department of Health, Disability and Ageing, $3 billion package for an additional 5,000 beds a year, with capital subsidies from 1 January 2027 and accommodation supplement increases from 20 March 2027
  3. Sector financial reporting: FY25 operating EBITDA of $5,647 per bed per annum against an estimated $20,000 to $22,000 required to be investable; more than 60 per cent of homes operating at a deficit with occupancy above 95 per cent