Build and open a residential aged care home — New South Wales
The same three-tier shape as childcare, with one difference that dominates everything else: the process is not what is stopping these being built. The economics are.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 1821 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 1155d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 330d | Someone is genuinely evaluating the merits. | |
| scheduling | 75d | Waiting for a person or committee to become available. | |
| statutory | 21d | A legislated period that must elapse regardless of readiness. |
75 of 1581 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A provider seeks to build and operate a new residential aged care home.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Site selection and financial feasibility
application
Identify a site, model the accommodation payment and subsidy revenue against construction and operating cost. |
— | applicant | — | 270 estimate | — |
| 2 |
Design and consultant documentation
application
Architectural documentation meeting the aged care design and accommodation requirements, plus traffic, acoustic and access reports. after
Site selection and financial feasibility 1071d slack
|
— | applicant | — | 240 estimate | — |
| 3 |
Lodge the development application
application
after
Design and consultant documentation 1066d slack
|
Consent authority (NSW council) | applicant | — | 5 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 4 |
Neighbour notification and submissions
notification
after
Lodge the development application 1045d slack
|
Consent authority (NSW council) | statutory | 14 | 21 estimate | — |
| 5 |
Council assessment
assessment
after
Neighbour notification and submissions 895d slack
|
Consent authority (NSW council) | assessment | — | 150 estimate | — |
| 6 |
Determination
decision
after
Council assessment 850d slack
|
Consent authority (NSW council) | scheduling | — | 45 estimate | — |
| 7 |
Construction certificate
certification
after
Determination 790d slack
|
Registered certifier (NSW) | assessment | — | 60 estimate | — |
| 8 |
Construction and fit-out
application
after
Construction certificate 150d slack
|
— | applicant | — | 640 estimate | — |
| 9 |
Occupation certificate
certification
after
Construction and fit-out 120d slack
|
Registered certifier (NSW) | assessment | — | 30 estimate | — |
| 10 |
Provider registration, or variation to add the service
registration
Registration in the applicable category under the Aged Care Act 2024, or a variation for an existing registered provider. after
Occupation certificate 30d slack
|
Aged Care Quality and Safety Commission | assessment | — | 90 estimate | Aged Care Act 2024 (Cth) |
| 11 |
Recruit to the care minute and registered nurse requirements
application
Staff to the sector-wide target of 215 care minutes per resident per day including 44 registered nurse minutes, and the 24/7 registered nurse requirement. after
Determination 610d slack
|
— | third party | — | 240 reported | — |
| 12 | Open and admit residents registration | — | scheduling | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- nsw-private-certifier (certification) appears at Construction certificate, Occupation certificate. Could these be a single sign-off?
Proposed changes
-
Universal registration: one aged care approval instead of two
merge
~90d The Aged Care Act 2024 merged provider approval and accreditation into a single registration in risk-based categories. It is the clearest counter-example to the assumption that merging approvals means weakening them — the same Act sharply increased the regulator's enforcement powers.
Sources
- Aged Care Act 2024 (Cth), commenced 1 November 2025, universal registration
- Department of Health, Disability and Ageing, $3 billion package for an additional 5,000 beds a year, with capital subsidies from 1 January 2027 and accommodation supplement increases from 20 March 2027
- Sector financial reporting: FY25 operating EBITDA of $5,647 per bed per annum against an estimated $20,000 to $22,000 required to be investable; more than 60 per cent of homes operating at a deficit with occupancy above 95 per cent
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/nsw-aged-care-home.toml and open a pull request, or
send us the correction.