An Australian SME becomes able to work on classified defence work
A circular dependency, written down. A firm needs cleared people to win classified work, and needs the work to justify clearing people. Nothing in the process is unreasonable on its own and the combination excludes almost everyone without a balance sheet.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 870 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| assessment | 390d | Someone is genuinely evaluating the merits. | |
|---|---|---|---|
| applicant | 240d | Waiting on the applicant to supply or fix something. | |
| queue | 150d | Waiting behind unrelated work in a backlog. | |
| scheduling | 30d | Waiting for a person or committee to become available. |
180 of 810 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A business needs to handle Defence classified information or assets, requiring DISP membership and cleared personnel.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Establish security governance and documentation
application
Security officer appointed, policies written, personnel and physical security procedures documented. |
— | applicant | — | 120 estimate | — |
| 2 |
Foreign ownership, control or influence assessment
assessment
Assessment of whether foreign ownership, control or influence disqualifies the business. after
Establish security governance and documentation 630d slack
|
Defence Industry Security Program and Defence Export Controls | assessment | — | 60 estimate | — |
| 3 |
Sponsor personnel security clearances
application
Nominate staff for the clearance level the intended work requires. after
Establish security governance and documentation 660d slack
|
Australian Government Security Vetting Agency | applicant | — | 30 estimate | — |
| 4 |
Security vetting
assessment
AGSVA assesses nominated personnel at Baseline, NV1 or NV2. after
Sponsor personnel security clearances 510d slack
|
Australian Government Security Vetting Agency | queue | — | 150 reported | — |
| 5 |
Facility accreditation and ICT system certification
certification
only if triggered Physical security accreditation of premises and certification of systems that will hold Defence information. Triggered when: The membership level sought requires classified storage or systems. Not required at Entry Level. after
Establish security governance and documentation 570d slack
|
Defence Industry Security Program and Defence Export Controls | assessment | — | 120 estimate | — |
| 6 |
DISP membership decision
registration
Defence decides the application for membership at the level sought.
|
Defence Industry Security Program and Defence Export Controls | assessment | — | 150 reported | — |
| 7 |
Respond to an ASDEFCON solicitation
application
Prepare a tender against the Australian Standard for Defence Contracting templates. after
DISP membership decision 270d slack
|
Department of Defence | applicant | — | 90 estimate | — |
| 8 |
Tender evaluation and contract negotiation
assessment
after
Respond to an ASDEFCON solicitation 30d slack
|
Department of Defence | assessment | — | 240 estimate | — |
| 9 |
Export permit for controlled goods or technology
referral
only if triggered Permit to export, re-export or transfer controlled goods, technology or services. Triggered when: The transfer is to a country outside Australia, the United Kingdom and the United States. Within AUKUS nations, most such transfers have required no licence since 1 September 2024.
|
Defence Industry Security Program and Defence Export Controls | assessment | — | 60 reported | — |
| 10 | Commence classified work registration | — | scheduling | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
Steps that may not need to wait
- Export permit for controlled goods or technology is a referral queued behind work by a different body. Does it consume that body's output, or is it merely sequenced that way by habit?
Proposed changes
-
AUKUS licence-free environment: a step deleted rather than accelerated
remove
~60d Since 1 September 2024 most controlled goods, technologies and services moving between Australia, the UK and the US need no export licence. The step is gone, not faster — the rarest and strongest reform type in this database. It still applies in full to everyone else.
-
Break the clearance circularity that keeps small firms out of defence
parallelise
~150d A firm needs cleared people to win classified work and needs the work to justify clearing people. The vetting standard is not the problem. Its position in the sequence is.
-
Match defence supplier accreditation to the information actually handled
threshold
~120d A supplier machining an unclassified part to a classified drawing is treated differently from one that never sees the drawing. Where the work can be structured so the supplier never holds classified information, the accreditation that protects classified information is protecting nothing.
Sources
- Department of Defence, published DISP application guidance: about 2-3 months for Entry Level, 4-6 months for Levels 1 to 3
- AGSVA, published performance information: NV1 approximately 3 months, NV2 approximately 5 months
- ANAO, Defence's Contract Administration -- Defence Industry Security Program
- Department of Defence, AUKUS national exemptions in force from 1 September 2024
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-defence-industry-entry.toml and open a pull request, or
send us the correction.