Build a multi storey apartment building — Australian Capital Territory

The longest pathway in the database: design review, a Class 2 building under the National Construction Code, fire engineering, extended referrals, and strata registration at the end.

developmentClass 2 residential apartment building, multi storey, site already held skeleton compare across jurisdictions
810 days elapsed
longest dependent chain
18 discrete steps
across 3 bodies
37% waiting on availability
scheduling or queue, not assessment
42 days saved by concurrency
vs. 852 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 304d Waiting on the applicant to supply or fix something.
assessment 210d Someone is genuinely evaluating the merits.
queue 181d Waiting behind unrelated work in a backlog.
scheduling 115d Waiting for a person or committee to become available.

296 of 810 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A Class 2 residential apartment building on a site the developer already controls, assessed by the local consent authority rather than as a state significant development.

#StepWhoWhy it waits ClockTypicalBasis
1 Prepare design and consultant documentation application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation.
— applicant — 300 estimate —
2 Design review panel assessment
An independent panel reviews the design against the applicable apartment design standards.
Territory Planning Authority scheduling — 45 estimate —
3 Fire engineering performance solution assessment only if triggered
Where the design departs from the deemed-to-satisfy provisions of the National Construction Code for a Class 2 building.
Triggered when: The design relies on a performance solution rather than deemed-to-satisfy provisions.
— assessment — 45 estimate —
4 Lodge the development application application Territory Planning Authority applicant — 3 published Planning Act 2023 (ACT)
5 Pay the assessment fee fee Territory Planning Authority applicant — 1 estimate —
6 Lodgement and properly-made check assessment
The authority checks the application is complete before assessment begins.
after Pay the assessment fee 440d slack
Territory Planning Authority queue — 21 estimate —
7 Public notification and submissions notification Territory Planning Authority statutory 28 28 estimate —
8 Internal and external referrals referral
Traffic, engineering, waste, landscape, heritage and state agency referrals, each responding separately.
Territory Planning Authority queue — 70 estimate —
9 Assessment against the planning rules assessment Territory Planning Authority assessment — 90 estimate Planning Act 2023 (ACT)
10 Information request and amended plans assessment only if triggered
The clock commonly stops while the applicant answers questions.
Triggered when: The authority requests further information.
Territory Planning Authority applicant — 90 estimate —
11 Determination and issue of development approval decision Territory Planning Authority scheduling — 45 estimate Planning Act 2023 (ACT)
12 Third party appeal period appeal only if triggered
A legislated window in which a submitter may seek review of the decision.
Triggered when: Submissions were received and a submitter has standing to seek review.
— statutory 28 28 estimate —
13 Pay development contributions fee Territory Planning Authority applicant — 14 estimate —
14 Obtain the building approval certification
Certifies that construction documentation complies with the National Construction Code and the planning approval.
Private building certifier (ACT) assessment — 75 estimate Building Act 2004 (ACT)
15 Mandatory inspections during construction inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time.
Private building certifier (ACT) scheduling — 25 estimate —
16 Obtain the certificate of occupancy and use certification
Authorises the building to be occupied.
Private building certifier (ACT) assessment — 45 estimate —
17 Obtain the strata certificate certification
Authorises registration of the plan creating separate titles. Cannot begin until the works are complete and certified.
Territory Planning Authority queue — 60 estimate —
18 Register the plan of strata registration
The land registry records the plan and issues the new titles.
Access Canberra Land Titles queue — 30 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

The same body asked more than once

Sources

  1. Australian Capital Territory published development assessment and building approval guidance, accessed 2026-08-30
  2. National Construction Code, Class 2 building requirements

Something wrong here?

This page is wrong in some way -- every page like it is. If you have run this process, the most useful thing you can do is tell us which step took longer than we say and why. Edit data/processes/act-apartments.toml and open a pull request, or send us the correction.