Build a block of townhouses — Western Australia
Scale changes the process qualitatively: mandatory public notification, multiple referrals, panel determination, development contributions and a subdivision that cannot start until the works are done.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 562 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| assessment | 185d | Someone is genuinely evaluating the merits. | |
|---|---|---|---|
| applicant | 154d | Waiting on the applicant to supply or fix something. | |
| queue | 134d | Waiting behind unrelated work in a backlog. | |
| scheduling | 47d | Waiting for a person or committee to become available. |
181 of 520 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: Multi-dwelling housing permitted with consent in the applicable zone, on a site the developer already controls.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Prepare design and consultant documentation
application
Architectural, civil, traffic, waste, landscape, stormwater and acoustic documentation. |
— | applicant | — | 150 estimate | — |
| 2 |
Lodge the development application
application
after
Prepare design and consultant documentation 367d slack
|
Local government (WA planning) | applicant | — | 3 published | Planning and Development Act 2005 (WA) |
| 3 |
Pay the assessment fee
fee
after
Lodge the development application 366d slack
|
Local government (WA planning) | applicant | — | 1 estimate | — |
| 4 |
Lodgement and properly-made check
assessment
The authority checks the application is complete before assessment begins. after
Pay the assessment fee 352d slack
|
Local government (WA planning) | queue | — | 14 estimate | — |
| 5 |
Public notification and submissions
notification
after
Lodgement and properly-made check 324d slack
|
Local government (WA planning) | statutory | 28 | 28 estimate | — |
| 6 |
Internal and external referrals
referral
Traffic, engineering, waste, landscape, heritage and state agency referrals, each responding separately. after
Lodgement and properly-made check 307d slack
|
Local government (WA planning) | queue | — | 45 estimate | — |
| 7 | Assessment against the planning rules assessment | Local government (WA planning) | assessment | — | 120 estimate | Planning and Development Act 2005 (WA) |
| 8 |
Information request and amended plans
assessment
only if triggered The clock commonly stops while the applicant answers questions. Triggered when: The authority requests further information. after
Assessment against the planning rules 97d slack
|
Local government (WA planning) | applicant | — | 90 estimate | — |
| 9 |
Determination and issue of development approval
decision
after
Assessment against the planning rules 152d slack
|
Local government (WA planning) | scheduling | — | 35 estimate | Planning and Development Act 2005 (WA) |
| 10 |
Third party appeal period
appeal
only if triggered A legislated window in which a submitter may seek review of the decision. Triggered when: Submissions were received and a submitter has standing to seek review. after
Determination and issue of development approval 124d slack
|
— | statutory | 28 | 28 estimate | — |
| 11 |
Pay development contributions
fee
after
Determination and issue of development approval 138d slack
|
Local government (WA planning) | applicant | — | 14 estimate | — |
| 12 |
Obtain the building permit
certification
Certifies that construction documentation complies with the National Construction Code and the planning approval. after
Determination and issue of development approval 112d slack
|
Building surveyor and permit authority (WA) | assessment | — | 40 estimate | Building Act 2011 (WA) |
| 13 |
Mandatory inspections during construction
inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time. after
Obtain the building permit 100d slack
|
Building surveyor and permit authority (WA) | scheduling | — | 12 estimate | — |
| 14 |
Obtain the notice of completion
certification
Authorises the building to be occupied. after
Mandatory inspections during construction 75d slack
|
Building surveyor and permit authority (WA) | assessment | — | 25 estimate | — |
| 15 |
Obtain the subdivision certificate
certification
Authorises registration of the plan creating separate titles. Cannot begin until the works are complete and certified. after
Obtain the notice of completion 30d slack
|
Local government (WA planning) | queue | — | 45 estimate | — |
| 16 |
Register the plan of subdivision
registration
The land registry records the plan and issues the new titles.
|
Landgate | queue | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- wa-building (certification) appears at Obtain the building permit, Obtain the notice of completion. Could these be a single sign-off?
- wa-planning (assessment) appears at Lodgement and properly-made check, Assessment against the planning rules, Information request and amended plans. Could these be a single sign-off?
Sources
- Western Australia published development assessment and building approval guidance, accessed 2026-08-30
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/wa-townhouses.toml and open a pull request, or
send us the correction.