Buy land and build a single storey house — Victoria
From choosing a lot to occupying the finished house: purchase, settlement, title, design, planning permit, building permit and occupancy permit.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 355 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 131d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 105d | Someone is genuinely evaluating the merits. | |
| third party | 80d | Waiting on an external body outside the regulator's control. | |
| queue | 7d | Waiting behind unrelated work in a backlog. | |
| scheduling | 5d | Waiting for a person or committee to become available. |
12 of 328 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: Buyer is purchasing a vacant residential lot and building one detached dwelling on it.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Find and select a lot
application
Search, inspect and choose a site. Entirely the buyer's own time. |
— | applicant | — | 60 estimate | — |
| 2 |
Sign the contract of sale
application
Contracts are exchanged or signed and the deposit is paid. after
Find and select a lot 261d slack
|
— | applicant | — | 7 estimate | — |
| 3 |
Statutory cooling-off period
decision
5 calendar days (approx) in which the buyer may rescind. after
Sign the contract of sale 256d slack
|
— | statutory | 5 | 5 reported | Planning and Environment Act 1987 (Vic) |
| 4 |
Unconditional finance approval
referral
The lender values the property and confirms the loan. after
Sign the contract of sale 240d slack
|
— | third party | — | 21 estimate | — |
| 5 |
Title, planning and site searches
assessment
Title search, planning certificate, contour and soil classification survey. after
Sign the contract of sale 240d slack
|
— | applicant | — | 21 estimate | — |
| 6 |
Pay transfer duty
fee
Stamp duty on the transfer, payable to the state revenue office. after
Sign the contract of sale 260d slack
|
— | applicant | — | 1 estimate | — |
| 7 |
Settlement period
registration
Customarily 45 days from contract to settlement in this jurisdiction.
|
Land Use Victoria | third party | — | 45 reported | — |
| 8 |
Transfer of title registered
registration
after
Settlement period 181d slack
|
Land Use Victoria | third party | — | 14 estimate | — |
| 9 |
Prepare design and consultant documentation
application
Architectural plans, siting, and a thermal performance assessment. after
Transfer of title registered 121d slack
|
— | applicant | — | 60 estimate | — |
| 10 |
Lodge the planning permit application
application
after
Prepare design and consultant documentation 118d slack
|
Responsible authority (Victorian council) | applicant | — | 3 published | Planning and Environment Act 1987 (Vic) |
| 11 |
Pay the assessment fee
fee
after
Lodge the planning permit application 117d slack
|
Responsible authority (Victorian council) | applicant | — | 1 estimate | — |
| 12 |
Lodgement and properly-made check
assessment
The authority checks the application is complete before assessment begins. after
Pay the assessment fee 110d slack
|
Responsible authority (Victorian council) | queue | — | 7 estimate | — |
| 13 |
Neighbour notification
notification
only if triggered Not generally required for a compliant single dwelling; triggered by variations to siting or height standards. Triggered when: The design departs from the acceptable siting, height or setback standards. after
Lodgement and properly-made check 96d slack
|
Responsible authority (Victorian council) | statutory | — | 14 estimate | — |
| 14 |
Internal and external referrals
referral
only if triggered Triggered by site-specific matters such as heritage, bushfire, flooding or a classified road frontage. Triggered when: The site attracts a referral trigger. after
Lodgement and properly-made check 82d slack
|
Responsible authority (Victorian council) | third party | — | 28 estimate | — |
| 15 |
Assessment against the planning rules
assessment
after
Lodgement and properly-made check 50d slack
|
Responsible authority (Victorian council) | assessment | 60 | 60 published | Planning and Environment Act 1987 (Vic) |
| 16 |
Information request and amended plans
assessment
only if triggered The clock commonly stops while the applicant answers questions. Triggered when: The authority requests further information. after
Assessment against the planning rules 5d slack
|
Responsible authority (Victorian council) | applicant | — | 45 estimate | — |
| 17 |
Determination and issue of planning permit
decision
after
Assessment against the planning rules 40d slack
|
Responsible authority (Victorian council) | assessment | — | 10 estimate | Planning and Environment Act 1987 (Vic) |
| 18 |
Obtain the building permit
certification
Certifies that construction documentation complies with the National Construction Code and the planning approval. after
Determination and issue of planning permit 19d slack
|
Building surveyor (Victoria) | assessment | — | 21 estimate | Building Act 1993 (Vic) |
| 19 |
Mandatory inspections during construction
inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time. after
Obtain the building permit 14d slack
|
Building surveyor (Victoria) | scheduling | — | 5 estimate | — |
| 20 |
Obtain the occupancy permit
certification
Authorises the building to be occupied.
|
Building surveyor (Victoria) | assessment | — | 14 estimate | — |
| 21 |
Utility connections
referral
only if triggered Water, sewer, power and telecommunications connections. Triggered when: The lot is not already serviced.
|
— | third party | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- vic-building (certification) appears at Obtain the building permit, Obtain the occupancy permit. Could these be a single sign-off?
- vic-planning (assessment) appears at Lodgement and properly-made check, Assessment against the planning rules, Information request and amended plans. Could these be a single sign-off?
Sources
- Victoria published development assessment and building approval guidance, accessed 2026-08-30
- Comparative state-by-state guides to contract cooling-off periods, accessed 2026-08-30
- Comparative state-by-state conveyancing settlement guides, accessed 2026-08-30
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/vic-buy-land-build-house.toml and open a pull request, or
send us the correction.