Buy land and build a single storey house — South Australia
From choosing a lot to occupying the finished house: purchase, settlement, title, design, planning consent, building consent and certificate of occupancy.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 314 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 131d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 80d | Someone is genuinely evaluating the merits. | |
| third party | 65d | Waiting on an external body outside the regulator's control. | |
| queue | 7d | Waiting behind unrelated work in a backlog. | |
| scheduling | 5d | Waiting for a person or committee to become available. |
12 of 288 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: Buyer is purchasing a vacant residential lot and building one detached dwelling on it.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Find and select a lot
application
Search, inspect and choose a site. Entirely the buyer's own time. |
— | applicant | — | 60 estimate | — |
| 2 |
Sign the contract of sale
application
Contracts are exchanged or signed and the deposit is paid. after
Find and select a lot 221d slack
|
— | applicant | — | 7 estimate | — |
| 3 |
Statutory cooling-off period
decision
4 calendar days (approx) in which the buyer may rescind. after
Sign the contract of sale 217d slack
|
— | statutory | 4 | 4 reported | Planning, Development and Infrastructure Act 2016 (SA) |
| 4 |
Unconditional finance approval
referral
The lender values the property and confirms the loan. after
Sign the contract of sale 200d slack
|
— | third party | — | 21 estimate | — |
| 5 |
Title, planning and site searches
assessment
Title search, planning certificate, contour and soil classification survey. after
Sign the contract of sale 200d slack
|
— | applicant | — | 21 estimate | — |
| 6 |
Pay transfer duty
fee
Stamp duty on the transfer, payable to the state revenue office. after
Sign the contract of sale 220d slack
|
— | applicant | — | 1 estimate | — |
| 7 |
Settlement period
registration
Customarily 30 days from contract to settlement in this jurisdiction.
|
Land Services SA | third party | — | 30 reported | — |
| 8 |
Transfer of title registered
registration
after
Settlement period 156d slack
|
Land Services SA | third party | — | 14 estimate | — |
| 9 |
Prepare design and consultant documentation
application
Architectural plans, siting, and a thermal performance assessment. after
Transfer of title registered 96d slack
|
— | applicant | — | 60 estimate | — |
| 10 |
Lodge the development application
application
after
Prepare design and consultant documentation 93d slack
|
Relevant authority (South Australia) | applicant | — | 3 published | Planning, Development and Infrastructure Act 2016 (SA) |
| 11 |
Pay the assessment fee
fee
after
Lodge the development application 92d slack
|
Relevant authority (South Australia) | applicant | — | 1 estimate | — |
| 12 |
Lodgement and properly-made check
assessment
The authority checks the application is complete before assessment begins. after
Pay the assessment fee 85d slack
|
Relevant authority (South Australia) | queue | — | 7 published | — |
| 13 |
Neighbour notification
notification
only if triggered Not generally required for a compliant single dwelling; triggered by variations to siting or height standards. Triggered when: The design departs from the acceptable siting, height or setback standards. after
Lodgement and properly-made check 71d slack
|
Relevant authority (South Australia) | statutory | — | 14 estimate | — |
| 14 |
Internal and external referrals
referral
only if triggered Triggered by site-specific matters such as heritage, bushfire, flooding or a classified road frontage. Triggered when: The site attracts a referral trigger. after
Lodgement and properly-made check 57d slack
|
Relevant authority (South Australia) | third party | — | 28 estimate | — |
| 15 |
Assessment against the planning rules
assessment
after
Lodgement and properly-made check 50d slack
|
Relevant authority (South Australia) | assessment | 35 | 35 published | Planning, Development and Infrastructure Act 2016 (SA) |
| 16 |
Information request and amended plans
assessment
only if triggered The clock commonly stops while the applicant answers questions. Triggered when: The authority requests further information. after
Assessment against the planning rules 5d slack
|
Relevant authority (South Australia) | applicant | — | 45 estimate | — |
| 17 |
Determination and issue of planning consent
decision
after
Assessment against the planning rules 40d slack
|
Relevant authority (South Australia) | assessment | — | 10 estimate | Planning, Development and Infrastructure Act 2016 (SA) |
| 18 |
Obtain the building consent
certification
Certifies that construction documentation complies with the National Construction Code and the planning approval. after
Determination and issue of planning consent 19d slack
|
Building certifier or accredited professional (SA) | assessment | — | 21 estimate | Planning, Development and Infrastructure Act 2016 (SA) |
| 19 |
Mandatory inspections during construction
inspection
Inspections at prescribed stages. Counted as booking delay only, not as construction time. after
Obtain the building consent 14d slack
|
Building certifier or accredited professional (SA) | scheduling | — | 5 estimate | — |
| 20 |
Obtain the certificate of occupancy
certification
Authorises the building to be occupied.
|
Building certifier or accredited professional (SA) | assessment | — | 14 estimate | — |
| 21 |
Utility connections
referral
only if triggered Water, sewer, power and telecommunications connections. Triggered when: The lot is not already serviced.
|
— | third party | — | 30 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- sa-building (certification) appears at Obtain the building consent, Obtain the certificate of occupancy. Could these be a single sign-off?
- sa-planning (assessment) appears at Lodgement and properly-made check, Assessment against the planning rules, Information request and amended plans. Could these be a single sign-off?
Sources
- South Australia published development assessment and building approval guidance, accessed 2026-08-30
- Comparative state-by-state guides to contract cooling-off periods, accessed 2026-08-30
- Comparative state-by-state conveyancing settlement guides, accessed 2026-08-30
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/sa-buy-land-build-house.toml and open a pull request, or
send us the correction.