Build a single house — Brisbane, accepted development plus building approval
Where a house complies with the planning scheme it may need no development application at all — only a building development approval from a certifier. The comparison with the NSW pathways is the point.
longest dependent chain
across 2 bodies
scheduling or queue, not assessment
vs. 68 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 38d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 25d | Someone is genuinely evaluating the merits. | |
| scheduling | 5d | Waiting for a person or committee to become available. |
5 of 68 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: The dwelling is accepted development under the planning scheme, so no planning application is required and only building approval is needed.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 | Prepare plans and engineering application | — | applicant | — | 35 estimate | — |
| 2 |
Engage a building certifier
application
after
Prepare plans and engineering 30d slack
|
Building certifier (Qld) | applicant | — | 3 estimate | — |
| 3 |
Siting variation or referral
referral
only if triggered Required where the design departs from the acceptable siting provisions, for example boundary setbacks. Triggered when: The design does not meet the acceptable outcomes for siting. after
Prepare plans and engineering 8d slack
|
Brisbane City Council — Development Services | queue | — | 25 estimate | — |
| 4 |
Building development approval
certification
after
Engage a building certifier 15d slack
|
Building certifier (Qld) | assessment | — | 15 estimate | Building Act 1975 (Qld) |
| 5 |
Mandatory inspections
inspection
after
Building development approval 10d slack
|
Building certifier (Qld) | scheduling | — | 5 estimate | — |
| 6 |
Final certificate
certification
after
Mandatory inspections
|
Building certifier (Qld) | assessment | — | 10 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Machine-flagged questions
These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.
The same body asked more than once
- qld-building-certifier (certification) appears at Building development approval, Final certificate. Could these be a single sign-off?
Sources
- Planning Act 2016 (Qld) — categories of development
- Building Act 1975 (Qld) — building development approvals
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/qld-dwelling-brisbane.toml and open a pull request, or
send us the correction.