Where a house complies with the planning scheme it may need no development application at all — only a building development approval from a certifier. The comparison with the NSW pathways is the point.

developmentSingle detached dwelling on an existing lot draft compare across jurisdictions
68 days elapsed
longest dependent chain
6 discrete steps
across 2 bodies
7% waiting on availability
scheduling or queue, not assessment
0 days saved by concurrency
vs. 68 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 38d Waiting on the applicant to supply or fix something.
assessment 25d Someone is genuinely evaluating the merits.
scheduling 5d Waiting for a person or committee to become available.

5 of 68 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: The dwelling is accepted development under the planning scheme, so no planning application is required and only building approval is needed.

#StepWhoWhy it waits ClockTypicalBasis
1 Prepare plans and engineering application — applicant — 35 estimate —
2 Engage a building certifier application Building certifier (Qld) applicant — 3 estimate —
3 Siting variation or referral referral only if triggered
Required where the design departs from the acceptable siting provisions, for example boundary setbacks.
Triggered when: The design does not meet the acceptable outcomes for siting.
Brisbane City Council — Development Services queue — 25 estimate —
4 Building development approval certification Building certifier (Qld) assessment — 15 estimate Building Act 1975 (Qld)
5 Mandatory inspections inspection Building certifier (Qld) scheduling — 5 estimate —
6 Final certificate certification Building certifier (Qld) assessment — 10 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Machine-flagged questions

These are produced automatically from the dependency graph. They are questions for a practitioner, not findings. Each one needs a person who has run this process to say whether the constraint is real.

The same body asked more than once

Sources

  1. Planning Act 2016 (Qld) — categories of development
  2. Building Act 1975 (Qld) — building development approvals