A state obtains Commonwealth capital for an urban public transport project
The business case and the construction are both excluded here. What is left is the Commonwealth decision chain — and its longest single wait is waiting for a Budget. At the end of it, the Commonwealth has paid for a structure and nobody has paid for a service.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 480 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| scheduling | 180d | Waiting for a person or committee to become available. | |
|---|---|---|---|
| assessment | 150d | Someone is genuinely evaluating the merits. | |
| third party | 120d | Waiting on an external body outside the regulator's control. | |
| applicant | 30d | Waiting on the applicant to supply or fix something. |
180 of 480 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A state or territory seeks Commonwealth capital contribution to an urban public transport project.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Submit the business case to Infrastructure Australia
application
Proposals seeking more than $250 million in Commonwealth funding are submitted for evaluation. |
Infrastructure Australia | applicant | — | 30 legislated | Infrastructure Australia Act 2008 (Cth) |
| 2 |
Infrastructure Australia evaluation
assessment
Independent assessment of the proposal's strategic fit, deliverability and economic case. after
Submit the business case to Infrastructure Australia 330d slack
|
Infrastructure Australia | assessment | — | 120 estimate | — |
| 3 |
Commonwealth Budget decision
decision
A funding commitment is made in a Budget. Budgets happen once a year. after
Infrastructure Australia evaluation 150d slack
|
Department of Infrastructure, Transport, Regional Development, Communications and the Arts | scheduling | — | 180 estimate | — |
| 4 |
Project funding agreement executed
registration
A project schedule under the Federation Funding Agreement on Land Transport Infrastructure Projects. after
Commonwealth Budget decision 30d slack
|
Department of Infrastructure, Transport, Regional Development, Communications and the Arts | third party | — | 120 estimate | — |
| 5 | First milestone payment registration | Department of Infrastructure, Transport, Regional Development, Communications and the Arts | assessment | — | 30 estimate | — |
| 6 |
Services run on the completed asset
registration
The Commonwealth's involvement ends at construction. The recurrent cost of running the service begins here and does not end. after
First milestone payment
|
State transport agency | assessment | — | 0 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Proposed changes
-
The longest wait in Commonwealth infrastructure funding is waiting for a Budget
resequence
~90d A proposal that clears evaluation in June is not refused. It waits for the next Budget. Same project, same merits, up to a year of difference depending on when the paperwork landed.
-
The only Commonwealth instrument for urban public transport can buy concrete and nothing else
threshold
$84 billion committed across 81 projects, $13.5 billion to the states in 2026-27, all of it paid against construction milestones. Fares recover 20 to 25 cents in the dollar of operating cost and the Commonwealth funds none of the rest.
Sources
- Infrastructure Australia Act 2008 (Cth)
- National Land Transport Act 2014 (Cth)
- Infrastructure Australia evaluates proposals that are nationally significant or seeking more than $250 million in Commonwealth investment, raised from $100 million
- Federation Funding Agreement Schedule on Land Transport Infrastructure Projects 2024-2029, in effect 11 August 2024
- Farebox recovery in Australian cities is around $0.20 to $0.25 of every $1 of operating expenditure
- The Infrastructure Investment Program provides capital funding to states and territories, paid against project milestones under project funding agreements
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-urban-transport-capital.toml and open a pull request, or
send us the correction.