Simple Wins / Australian Red Tape Every step, every clock, every authority -- written down.

A state obtains Commonwealth capital for an urban public transport project

The business case and the construction are both excluded here. What is left is the Commonwealth decision chain — and its longest single wait is waiting for a Budget. At the end of it, the Commonwealth has paid for a structure and nobody has paid for a service.

infrastructureOne major urban public transport project above the Infrastructure Australia evaluation threshold skeleton compare across jurisdictions
480 days elapsed
longest dependent chain
6 discrete steps
across 3 bodies
38% waiting on availability
scheduling or queue, not assessment
0 days saved by concurrency
vs. 480 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

scheduling 180d Waiting for a person or committee to become available.
assessment 150d Someone is genuinely evaluating the merits.
third party 120d Waiting on an external body outside the regulator's control.
applicant 30d Waiting on the applicant to supply or fix something.

180 of 480 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A state or territory seeks Commonwealth capital contribution to an urban public transport project.

#StepWhoWhy it waits ClockTypicalBasis
1 Submit the business case to Infrastructure Australia application
Proposals seeking more than $250 million in Commonwealth funding are submitted for evaluation.
Infrastructure Australia applicant — 30 legislated Infrastructure Australia Act 2008 (Cth)
2 Infrastructure Australia evaluation assessment
Independent assessment of the proposal's strategic fit, deliverability and economic case.
Infrastructure Australia assessment — 120 estimate —
3 Commonwealth Budget decision decision
A funding commitment is made in a Budget. Budgets happen once a year.
Department of Infrastructure, Transport, Regional Development, Communications and the Arts scheduling — 180 estimate —
4 Project funding agreement executed registration
A project schedule under the Federation Funding Agreement on Land Transport Infrastructure Projects.
Department of Infrastructure, Transport, Regional Development, Communications and the Arts third party — 120 estimate —
5 First milestone payment registration Department of Infrastructure, Transport, Regional Development, Communications and the Arts assessment — 30 estimate —
6 Services run on the completed asset registration
The Commonwealth's involvement ends at construction. The recurrent cost of running the service begins here and does not end.
State transport agency assessment — 0 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Proposed changes

Sources

  1. Infrastructure Australia Act 2008 (Cth)
  2. National Land Transport Act 2014 (Cth)
  3. Infrastructure Australia evaluates proposals that are nationally significant or seeking more than $250 million in Commonwealth investment, raised from $100 million
  4. Federation Funding Agreement Schedule on Land Transport Infrastructure Projects 2024-2029, in effect 11 August 2024
  5. Farebox recovery in Australian cities is around $0.20 to $0.25 of every $1 of operating expenditure
  6. The Infrastructure Investment Program provides capital funding to states and territories, paid against project milestones under project funding agreements