Simple Wins / Australian Red Tape Every step, every clock, every authority -- written down.

A household installs rooftop solar and is permitted to export

Network approval takes three to ten business days and the installation takes one. Then the system sits on the roof, generating, not permitted to export, waiting for a meter that a party the household never chose has fifteen business days to deliver and often does not.

energyOne standard residential system, up to 10 kW single-phase, on an existing home draft compare across jurisdictions
58 days elapsed
longest dependent chain
9 discrete steps
across 4 bodies
52% waiting on availability
scheduling or queue, not assessment
21 days saved by concurrency
vs. 79 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

queue 30d Waiting behind unrelated work in a backlog.
applicant 17d Waiting on the applicant to supply or fix something.
assessment 10d Someone is genuinely evaluating the merits.
third party 1d Waiting on an external body outside the regulator's control.

30 of 58 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A household contracts to install a rooftop solar system and wants to export to the grid.

#StepWhoWhy it waits ClockTypicalBasis
1 Quote from an accredited installer application
The subsidy is applied here, at the point of sale, by the installer.
Solar Accreditation Australia applicant — 14 estimate —
2 Network connection approval application
Pre-approval to connect embedded generation, with an export limit attached.
Distribution network service provider assessment — 7 published —
3 Installation inspection
The physical work. One day.
— third party — 1 estimate —
4 Certificate of electrical safety and compliance certification
Lodged by the licensed electrician under state law.
after Installation 33d slack
— applicant — 3 estimate —
5 Certificates created and validated registration Clean Energy Regulator third party — 21 estimate —
6 Meter installed or reconfigured inspection
A bidirectional meter, arranged by the retailer, performed by a metering coordinator the household did not choose.
Metering coordinator queue 21 30 p90 60d reported —
7 Network authorises export decision Distribution network service provider assessment — 3 estimate —
8 Emergency backstop capability enabled certification
Remote curtailment capability, required by AEMO, legislated five separate times on five separate dates.
Distribution network service provider assessment — 0 published —
9 System exporting and credited registration — assessment — 0 estimate —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Proposed changes

Sources

  1. For standard residential systems up to 10 kW single-phase or 30 kW three-phase, DNSP connection approval typically takes 3-10 business days
  2. Almost every distribution network service provider in Australia caps solar exports at 5 kW per phase
  3. The retailer assigns a metering coordinator to install a bidirectional meter; only once the meter is in place and the DNSP authorises can the system legally export
  4. From 1 February 2019 regulations required digital meters to be installed within 15 business days
  5. Energy and Water Ombudsman NSW case: more than 40 business days after notification that a smart meter needed reconfiguration
  6. Cheaper Home Batteries Program: SRES extended to batteries between 5 kWh and 100 kWh from 1 July 2025, delivering around a 30 per cent discount