A freight train already built is approved to run from Melbourne to Brisbane
Rail safety was nationalised in 2013 and one regulator accredits the operator. What the vehicle must meet is still settled network by network, so the same evidence is assessed four times. The build is not modelled here — the approval alone is eighteen months.
longest dependent chain
across 2 bodies
scheduling or queue, not assessment
vs. 720 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| statutory | 180d | A legislated period that must elapse regardless of readiness. | |
|---|---|---|---|
| assessment | 120d | Someone is genuinely evaluating the merits. | |
| queue | 90d | Waiting behind unrelated work in a backlog. | |
| third party | 60d | Waiting on an external body outside the regulator's control. | |
| scheduling | 60d | Waiting for a person or committee to become available. | |
| applicant | 30d | Waiting on the applicant to supply or fix something. |
150 of 540 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: An operator has rolling stock and wants to run it across networks managed by more than one rail infrastructure manager.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Engineering design assurance against the first network's interface standards
certification
Gauge, axle load, clearance envelope, braking, coupling and signalling interface, assessed against one manager's standards. |
Australian Rail Track Corporation | assessment | — | 120 estimate | — |
| 2 |
Accreditation, or variation of accreditation, granted
application
The national decision that the operator is competent and capable of managing the safety risks of the operation.
|
Office of the National Rail Safety Regulator | statutory | 180 | 180 legislated | Rail Safety National Law |
| 3 |
Interoperability Management Plan prepared and incorporated
certification
A new requirement in full effect from 28 February 2026 for operators on the National Network for Interoperability. after
Accreditation, or variation of accreditation, granted 210d slack
|
Office of the National Rail Safety Regulator | applicant | — | 30 published | — |
| 4 |
Certification and registration with the interstate network manager
registration
after
Interoperability Management Plan prepared and incorporated 150d slack
|
Australian Rail Track Corporation | third party | — | 60 estimate | — |
| 5 | Acceptance by the New South Wales metropolitan network manager registration | — | queue | — | 90 estimate | — |
| 6 | Acceptance by the Victorian metropolitan network manager registration | — | queue | — | 90 estimate | — |
| 7 | Acceptance by the Queensland network manager registration | — | queue | — | 90 estimate | — |
| 8 | Crew route knowledge and network rules competency certification | — | scheduling | — | 60 estimate | — |
| 9 | Vehicle in interstate service registration | — | assessment | — | 0 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Proposed changes
-
This is what harmonisation actually costs when someone genuinely does it
resequence
Rail interoperability was made a national priority in 2020. The first mandatory requirements took effect in February 2026. A mandatory national rolling stock approvals standard is scheduled for 2029-2030. Ten years, for a process standard.
-
The independent review blamed the proponent's own documents, not the regulator
resequence
Inland Rail went from $16.4 billion to over $45 billion and 2036. A red tape database would expect to find environmental approvals at the centre of that. The Schott review found immature design and poor environmental impact statements requiring resubmission.
-
Automatic mutual recognition exists for people and not for trains
merge
~90d Rail safety was nationalised in 2013 and works: one law, one regulator, one accreditation. What a vehicle must meet was not, so the same test reports are assessed by four infrastructure managers against four sets of interface standards.
Sources
- National Transport Commission: in Australia it can take less time to build a train than it does to get it approved to run across the country, which creates significant barriers to investment
- ONRSR: must decide to grant or refuse an application for accreditation within six months of receiving it; a variation of accreditation is assessed in the same way as an accreditation
- ONRSR: new requirements for the interoperability of railway operations took full effect on 28 February 2026; operators on the National Network for Interoperability must prepare an Interoperability Management Plan as part of their safety management system
- NTC: variation in interface standards across jurisdictions creates cost and duplication; Stage 3 (2029-2030) develops a mandatory national standard for rolling stock approvals
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-rolling-stock-approval.toml and open a pull request, or
send us the correction.