Mobile coverage reaches a place the market will not serve

Seven rounds, more than a billion dollars, up to 1,400 base stations — and from December 2027 an obligation that would require coverage everywhere regardless. Two instruments for one problem, running at the same time.

telecommunicationsA single new base station in a regional or remote location, delivered through the co-investment programs draft compare across jurisdictions
940 days elapsed
longest dependent chain
7 discrete steps
across 3 bodies
19% waiting on availability
scheduling or queue, not assessment
0 days saved by concurrency
vs. 940 if run end-to-end

Where the time goes

Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.

applicant 490d Waiting on the applicant to supply or fix something.
scheduling 180d Waiting for a person or committee to become available.
assessment 150d Someone is genuinely evaluating the merits.
third party 120d Waiting on an external body outside the regulator's control.

180 of 940 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.

The process, step by step

Applies when: A location has no adequate mobile coverage and no carrier will build there commercially.

#StepWhoWhy it waits ClockTypicalBasis
1 The location has no coverage assessment
A place where coverage is absent and no carrier will build commercially.
— assessment — 0 estimate —
2 Community or council nominates the location application
Locations are nominated for consideration in a funding round.
Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts applicant — 90 estimate —
3 Wait for a funding round registration
Applications are accepted in competitive rounds.
Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts scheduling — 180 published —
4 A carrier bids for the location application
A mobile network operator decides whether to include the site in a bid.
after Wait for a funding round 550d slack
Mobile network operator third party — 120 estimate —
5 Assessment and co-investment rate set assessment
Funding share determined by how many operators will share the infrastructure.
Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts assessment — 150 published —
6 Build and commission the site application Mobile network operator applicant — 400 estimate —
7 Universal Outdoor Mobile Obligation commences decision only if triggered
From 1 December 2027, carriers required to provide baseline outdoor voice and SMS coverage across Australia.
Triggered when: The obligation commences and covers the location, making the co-investment pathway unnecessary for baseline voice and SMS.
Australian Communications and Media Authority statutory — 365 published —

on the critical path   scheduling/queue = delay not caused by the assessment itself

Proposed changes

Sources

  1. Mobile Black Spot Program: seven rounds, more than $1 billion invested, up to 1,400 new mobile base stations, with co-contributions from state and local governments and mobile network operators
  2. Regional Connectivity Program Round 3 of $100 million and Mobile Black Spot Round 7 of $50 million; Round 8 awarded $21.1 million, closing for applications 28 August 2026
  3. Co-investment rates: up to 100 per cent for projects involving all three national mobile network operators using active sharing or roaming; 50 to 75 per cent for co-location or fewer operators; $22.5 million for First Nations solutions contributing toward Closing the Gap Target 17
  4. Universal Outdoor Mobile Obligation announced 25 February 2025, requiring Telstra, Optus and TPG to provide reasonable and equitable access to baseline outdoor mobile coverage from 1 December 2027