A social housing project funded under the Housing Australia Future Fund
The Commonwealth funding layer sits on top of the entire ordinary development chain, and adds a competitive round to the front of it. Under 4 per cent of the 40,000 home target had been delivered by May 2026.
longest dependent chain
across 3 bodies
scheduling or queue, not assessment
vs. 2390 if run end-to-end
Where the time goes
Critical-path days only. Steps that run alongside others are real work but do not lengthen the process, so counting them here would overstate the prize.
| applicant | 1072d | Waiting on the applicant to supply or fix something. | |
|---|---|---|---|
| assessment | 761d | Someone is genuinely evaluating the merits. | |
| scheduling | 137d | Waiting for a person or committee to become available. | |
| third party | 120d | Waiting on an external body outside the regulator's control. |
137 of 2090 elapsed days are spent waiting for a person or a meeting rather than for a judgement to be formed. Removing that time changes no assessment standard and lowers no bar -- it is the cost of scheduling alone.
The process, step by step
Applies when: A community housing provider seeks Commonwealth funding to deliver new social and affordable homes.
| # | Step | Who | Why it waits | Clock | Typical | Basis |
|---|---|---|---|---|---|---|
| 1 |
Hold community housing provider registration at the required tier
registration
Registration under the national system, or under the separate Victorian or Western Australian systems. |
National Regulatory System for Community Housing | assessment | — | 270 estimate | — |
| 2 |
Secure a site and develop a scheme
application
Land acquisition or a state land transfer, feasibility, and design to a level that can be costed and bid. after
Hold community housing provider registration at the required tier 1455d slack
|
— | applicant | — | 365 estimate | — |
| 3 |
Wait for a funding round to open
registration
Applications are accepted in competitive rounds rather than continuously. after
Secure a site and develop a scheme 1318d slack
|
Housing Australia | scheduling | — | 137 published | — |
| 4 |
Prepare and lodge the funding application
application
after
Wait for a funding round to open 1251d slack
|
Housing Australia | applicant | — | 67 published | — |
| 5 |
Assessment and contracting
assessment
Assessment of the proposal and negotiation of the funding agreement. after
Prepare and lodge the funding application 880d slack
|
Housing Australia | assessment | — | 371 published | — |
| 6 |
Development approval
decision
The ordinary planning consent process, unchanged by the presence of Commonwealth funding. after
Secure a site and develop a scheme 1155d slack
|
Consent authority (NSW council) | assessment | — | 300 estimate | Environmental Planning and Assessment Act 1979 (NSW) |
| 7 |
Financial close
decision
Debt, equity and Commonwealth support brought together against a costed, consented scheme.
|
— | third party | — | 120 estimate | — |
| 8 |
Construction
application
after
Financial close 120d slack
|
— | applicant | — | 640 estimate | — |
| 9 |
Completion, certification and tenanting
certification
after
Construction
|
— | assessment | — | 120 estimate | — |
on the critical path scheduling/queue = delay not caused by the assessment itself
Proposed changes
-
Finish the national community housing register
remove
~120d A national registration scheme for community housing providers that Victoria and Western Australia are not in — while the Commonwealth funds providers to operate across exactly those borders.
-
Settle the governance before opening the funding round, not two years after
resequence
Housing Australia Future Fund applications opened in January 2024. Treasury did not finalise most delivery and oversight arrangements until May 2026. This is the counter-case to almost everything else on this site: a step that happened too early.
Sources
- ANAO performance audit of the Housing Australia Future Fund, July 2026: applications opened January 2024, most governance and oversight arrangements not finalised until May 2026
- Reported delivery of 1,432 homes against a 40,000 target as at May 2026, comprising 762 newly constructed and 670 purchased
- NRSCH, published registration categories and tier criteria
- Auditor-General Report No.3 2026-27, Department of the Treasury's Design and Delivery of the Housing Australia Future Fund and the National Housing Accord Facility, Australian National Audit Office, https://www.anao.gov.au/sites/default/files/2026-07/Auditor-General_Report_2026-27_3.pdf, accessed 2026-11-09
Something wrong here?
This page is wrong in some way -- every page like it is. If you have run
this process, the most useful thing you can do is tell us which step took
longer than we say and why. Edit
data/processes/au-haff-project.toml and open a pull request, or
send us the correction.