How many homes has the Housing Australia Future Fund actually finished, and where are they?
Housing Australia publishes financing decisions and contracted progress. Treasury reports the housing programs only in aggregate, and the completions figure -- 1,432 as at April 2026 -- reached the public through an audit. The ANAO has recommended publishing delivery against forecast.
Why it matters
This is the largest housing commitment the Commonwealth has made in a generation, $10 billion against a target of 20,000 social and 20,000 affordable homes, and the number that tests it is completions.
Some reporting exists and the register should be accurate about it. The Housing Australia Investment Mandate requires Housing Australia to publish detail within six months of a financing decision, and it does; it also maintains a page describing overall progress on contracted dwellings. So a reader can establish what has been committed and, broadly, to whom.
Completions are a different matter. The Auditor-General found that Treasury "publicly reports on the overall delivery of social and affordable housing" but that the reporting covers the Future Fund, the National Housing Accord Facility and the Social Housing Accelerator "in aggregate", and "does not report separately on the performance of the individual programs". The figure that prompted most of the public argument -- 1,432 homes completed as at April 2026, against 40,000 -- appears in the audit, in a table the audit had to construct.
The data exists on a quarterly cycle. The ANAO's fifth recommendation asks Treasury to report publicly on program performance, and gives as candidate measures "dwellings delivered versus forecast deliveries" and information similar to the quarterly reporting Treasury already provides to government. Treasury agreed. So the internal series exists, the auditor has recommended publishing it, and the department has accepted the recommendation.
Can it be answered?
What stands in the way
| Obstruction | What it means here |
|---|---|
| aggregated | Published only at a level too coarse to answer the question asked. |
| not published | The body holds this and does not release it. Nothing new would have to be collected. |
Every obstruction above is a decision about how to publish, not a fact about what exists or a limit on what may lawfully be released. This question could be answered without collecting anything new.
Data that bears on this
Two things could be true and the register cannot yet tell them apart: the data may not be published, or it may be published somewhere we have not looked. If it is the second, saying so is worth more than a new entry.
How people get at it anyway
Housing Australia's financing decision disclosures and its contracted-progress page give commitments. The ANAO performance audit is the practical source for a completions figure, and is a point-in-time document produced on the audit office's schedule rather than the program's.
State governments and providers announce individual projects, allowing a partial bottom-up reconstruction that is incomplete by construction.
Notes
Marked verified on 2026-09-03: the audit report was downloaded and its text
searched, not read about. Table 2.3 gives 1,432 completed, paragraph 3.125 carries
the words "does not report separately on the performance of the individual
programs", and the summary page states Treasury's $770,387 estimate of average
government support per dwelling over 25 years.
Checked against the audit report on 2026-09-01, which confirmed the entry and narrowed it.
The completions figure and the aggregation finding are both verified: Table 2.3 records 1,432 completed for rounds one and two and none for round three, and paragraph 3.125 carries the aggregate-reporting finding in the words quoted above. Recommendation 5 and Treasury's agreement to it are as described.
What the check corrected is the implication that nothing is published at
project level. Housing Australia's Investment Mandate disclosures are real and
were not accounted for in the first draft, so fragmented has been dropped and
the entry now claims only what the audit supports: performance and completions
are not reported per program or per project, while commitments largely are.
This is among the strongest cases in the register precisely because none of it is contested. The data is collected quarterly, the auditor has recommended publishing it, and the department has agreed. What remains is for the agreed recommendation to be implemented, which is a matter of record rather than argument.
The contrast worth keeping beside this entry is the Clean Energy Regulator's small-scale technology data, which reports household battery uptake by postcode on a rolling basis. Same government, same year, same question shape -- how much of the thing has happened, and where.
Related: Did the $2 billion Social Housing Accelerator buy homes that would not otherwise have been built?, How many social housing dwellings are vacant, and for how long, by area?.
Sources
- ANAO, Department of the Treasury's Design and Delivery of the Housing Australia Future Fund and the National Housing Accord Facility, Auditor-General Report No.3 2026-27 (Table 2.3, paragraphs 3.125 to 3.130 and Recommendation 5), opened and searched 2026-09-01
- Housing Australia, funding round disclosures made under the Housing Australia Investment Mandate Direction 2018
Know better?
If this data is published somewhere and we have missed it, saying so
improves the register more than adding a new question would — a false gap is
worse than no entry. Edit data/questions/haff-homes-delivered.toml, or
send the correction.